Aashish Promoters & Builders
Deedo IDDD-DCX6Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| NandanvanP52100015733 | Haveli | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | +49 mo* |
| Yashashree IIP52100020984 | Katraj | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
Aashish Promoters & Builders, in questions
Does Aashish Promoters & Builders finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aashish Promoters & Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Aashish Promoters & Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.