Aarambha Vision Homes Private Limited
Deedo IDDD-BZD3Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aarambha HeightsP51700017982 | Dombivli | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | +56 mo* |
| Aarambha AnnexP51700045671 | Kalyan-Dombivali (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| Aarambha CrystalPM1330002600472 | Gajbandhan Patharli | Certificate Signed | 30 Jun 2030 | 30 Oct 2030 | +4 mo |
Aarambha Vision Homes Private Limited, in questions
Does Aarambha Vision Homes Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aarambha Vision Homes Private Limited registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Aarambha Vision Homes Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.