Company or firm · first RERA registration 2021

Aaradhya Construction

Deedo IDDD-BSVH

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 6 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay6 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shreeji ParkP52800030592Nachane (Ct)Certificate Signed3 May 20263 Sep 2026+6 mo*

Aaradhya Construction, in questions

Does Aaradhya Construction finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.

How many projects has Aaradhya Construction registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Aaradhya Construction have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology