Aakruti Builders & Developers
Deedo IDDD-RY7SOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aakruti Building No. 4 And 5P52000005056 | Pen (M Cl) | Certificate Signed | 30 Jun 2021 | 31 Mar 2023 | +21 mo |
| Aakruti Building No.2P52000012245 | Pen (M Cl) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
Aakruti Builders & Developers, in questions
Does Aakruti Builders & Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aakruti Builders & Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Aakruti Builders & Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.