Aaditya Lifespaces Infraventure Pvt Ltd
Deedo IDDD-7FS5Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 93 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gangwani GardensP50500015680 | Bhilgaon | Certificate Signed | 21 Mar 2018 | 31 Dec 2025 | +93 mo |
Aaditya Lifespaces Infraventure Pvt Ltd, in questions
Does Aaditya Lifespaces Infraventure Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 93 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aaditya Lifespaces Infraventure Pvt Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Aaditya Lifespaces Infraventure Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.