Deedo IDDD-YPD5Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 32 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Redevelopment NupurP51800032250 | Kurla | Certificate Signed | 31 Mar 2024 | 30 Mar 2025 | +32 mo* |
A & A Aristocrate Realty Private Limited, in questions
Does A & A Aristocrate Realty Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 32 mo late. Across Maharashtra, 73% kept their date.
How many projects has A & A Aristocrate Realty Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does A & A Aristocrate Realty Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.