RERA projects in Brahmapuri

63 projects under 64 MahaRERA registrations, registered 2017–2026. 18% have a completion date extended beyond the one promised.

Taluka
63RERA projects
64Registrationssome projects hold several
10Completion still due50 past their completion date, 14 marked completed
4 monthsMedian extension beyond promised date18% of registrations extended
0Regulatory casesnone on MahaRERA's lists
20Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20177
20182
20193
20207
202110
202214
20234
20249
20253
20261

Projects in Brahmapuri

63 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
DelanwadiPrabhakar N Pilare and 4 othersP5090003335616 Feb 202231 Mar 202331 Mar 2023Promised date passed0
Vaibhav Laxmi NagariGangadhar Harihar BhupalP509000331839 Feb 202231 Mar 202231 Mar 2022Promised date passed0
Pilare LayoutRajesh Deoraoji PilareP5090003254910 Jan 202231 Mar 202431 Mar 2024Promised date passed0
Shree Ambaji NagarBhikubhai K Lodhiya ,Namitaben B lodhiya , Pankaj B Lodhiya, Varun B LodhiyaP5090003252710 Jan 202231 Mar 202531 Mar 2025Promised date passed0
Gurudevnagari LayoutAshish M Karande and Anjali A KarandeP509000324174 Jan 202231 Mar 202331 Mar 2023Promised date passed0
Radha Krushna NagariAshok Kisanlal BhaiyyaP509000320623 Dec 202131 Mar 202231 Mar 2024Extended 24 mo0
Gat No 114Prabhakar Narayan Pilare and 4 othersP5090003148725 Oct 202131 Mar 202431 Mar 2024Promised date passed0
Vasavi 4Vasavi DevelopersP5090003133823 Oct 202131 Jul 202231 Jul 2024Extended 24 mo0
Vasavi Developers Gat No 801Vasavi DevelopersP5090003027315 Aug 202131 Mar 202231 Mar 2022Promised date passed0
Aradhy Nagri KhedNayeem Abbas Sherali JiwaniP509000302205 Aug 202131 Mar 202231 Mar 2022Promised date passed0
Gaurav Nagari 2PMG AssociatesP5090002977329 Jun 202131 Dec 202431 Dec 2024Promised date passed0
Shree Niwas ApartmentShree Gurukrupa Builders And DevelopersP5090002879530 Mar 202130 Jun 202330 Jun 2023Promised date passed0
Astha NagriShakuntala Shamrao UradeP5090002835318 Feb 202130 Sep 202230 Sep 2022Promised date passed0
Gajanan NagariPMG AssociatesP5090002797021 Jan 202130 Sep 202230 Sep 2022Promised date passed0
Shree Sai Krupa LayoutAmit Vasantrao MendhuleP5090002797721 Jan 202130 Sep 202230 Sep 2022Promised date passed0
Sidheshwar NagariSidheshwar Bhayyaji Bharre And Yogesh Balaji MisarP5090002719324 Nov 202030 Sep 202230 Sep 2022Promised date passed0
Sai NagariRajendra Arjun ShetiyaP5090002708813 Nov 202030 Sep 202230 Sep 2022Promised date passed0
Urkude Nagari -2Manohar Marotrao UrkudeP5090002634211 Sep 202030 Jun 202230 Jun 2022Promised date passed0
Shri SaiVinod Nawghade and Rajendra NimjeP5090002513118 Mar 202030 Mar 2022—Promised date passed0
Shree Gurukrupa LayoutAnup Mendhule, Sarang Mendhule & Husain Abid KaroriP5090002456424 Feb 202030 Mar 2022—Completed0
Vaibhav LaxmiNamdeo T Kapgate, Meghendra H kapgate & Ravikumar H SonwaneP509000243013 Feb 202030 Mar 202230 Mar 2022Promised date passed0
Urkude Nagari - 1VINODINI MANOHAR UrkudeP509000238106 Jan 202030 Sep 2020—Completed0
Bokade layoutMahendra Shrawanji Bokade & OthersP5090002357119 Dec 201930 Mar 202430 Mar 2025Completed0
Gaurav NagariSatish D Humne & Taufik N PathanP5090002213728 Aug 201930 Mar 2022—Completed0
Matai NagarShri. Ashish Madanrao karande and Sau. Anjali Ashish KarandeP5090001997015 Mar 201930 Dec 2021—Completed0

Other talukas in Chandrapur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vidarbha Town Developers6 projects
  2. PMG Associates5 projects
  3. Shree Gurukrupa Builders And Developers4 projects
  4. Amit Vasantrao Mendhule2 projects
  5. Ashish M Karande and Anjali A Karande2 projects
  6. Vasavi Developers2 projects
  7. Yogesh Balaji Misar2 projects
  8. Akshay Hajare, Mahadeo Hajare, Saraswati Hajare & Madhao Hajare1 project
  9. Anjali Ashish Karande1 project
  10. Anuj Vasantrao Mendhule1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology