RERA projects in Shegaon
8 projects under 8 MahaRERA registrations, registered 2020–2025. 40% have a completion date extended beyond the one promised.
Taluka
8RERA projects
8Registrations
0Completion still due5 past their completion date, 2 marked completed
15 monthsMedian extension beyond promised date40% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 2 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
Projects in Shegaon
8 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| SwamiAditya Anagha Multi State Credit Co-Operative Society Limited | P50000081048 | 24 Nov 2025 | 31 May 2026 | — | Promised date passed | 0 |
| Shri Gajanan TowersShri Gajanan Towers | P50000034277 | 30 Mar 2022 | 10 Dec 2022 | 10 Dec 2023 | Extended 12 mo | 0 |
| Shree Jalaram HeightsNitinkumar Chhaganlal Ganatra | P50000032877 | 2 Feb 2022 | 31 Dec 2024 | — | Completed | 0 |
| Sai Gajanan TowersM/s Sai Gajanan Towers | P50000025263 | 31 Mar 2020 | 30 Dec 2021 | — | Completed | 0 |
| Gurukripa ChambersKailash Bhagwandas Sharma | P50000023687 | 2 Jan 2020 | 30 Jun 2021 | 30 Dec 2022 | Extended 18 mo | 0 |
| P50000026629 | P50000026629 | — | — | — | — | 0 |
| P50000027677 | P50000027677 | — | — | — | — | 0 |
| P50000027938 | P50000027938 | — | — | — | — | 0 |
Other talukas in Buldana
Most active promoters
By projects registered here, as named on MahaRERA.
- Aditya Anagha Multi State Credit Co-Operative Society Limited1 project
- Kailash Bhagwandas Sharma1 project
- M/s Sai Gajanan Towers1 project
- Nitinkumar Chhaganlal Ganatra1 project
- Shri Gajanan Towers1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology