RERA projects in Malkapur

2 projects under 2 MahaRERA registrations, registered 2018–2018. 100% have a completion date extended beyond the one promised.

2RERA projects
2Registrations
0Completion still due1 past their completion date, 1 marked completed
24 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181

Projects in Malkapur

2 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
AashrayVyankateshwara AssociatesP5000001755928 Aug 201831 Dec 201930 Dec 2021Completed0
P50000030840P50000030840————0

Other talukas in Buldana

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vyankateshwara Associates1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology