Skip to content
Residential / Group Housing · 5 buildings · 45 unitsRERA P51500024945

Unity Park

Deedo IDDP-AUR-QX37

Completion was pushed back 2 years and 5 months, to May 2027; no MahaRERA orders on record; 29% of its units are booked.

Tisgaon, Aurangabad 431136 · by Baheti Landmark

DeliveryExtended 2 yrs 5 moPromised Dec 2024 · now due May 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales29% booked13 of 45 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 2 years and 5 months, to May 2027

  • This projectRegistered 12 Mar 2020, completion promised 30 Dec 2024, revised to 31 May 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51500024945
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150002494512 Mar 202030 Dec 202431 May 2027Baheti LandmarkProject page
Documents181

76 documents held by Deedo, 105 filings listed on MahaRERA's project page

Registration certificate

Other (75)

Show all 181 documentsShow fewer documents

Other (75)

Legal

  • Legal Title reporttitle report.pdf · uploaded 14 Feb 2020Source
  • Legal Title reporttitle report.pdf · uploaded 14 Feb 2020Source
  • Declaration Form Bform b affidavit.pdf · uploaded 17 Feb 2020Source
  • Otherpower of attorney Complete.pdf · uploaded 11 Mar 2020Source
  • Declaration Form BForm B Affidavit.pdf · uploaded 14 Dec 2024Source
  • OtherClarification about delay.pdf · uploaded 17 Dec 2024Source

Migrated

  • 1 Details of encumbrancesDETAILS OF ENCUMBRANCES.pdf · uploaded 8 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT APPROVAL.pdf · uploaded 8 Jan 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentapproved building plan_compressed.pdf · uploaded 8 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE (2).pdf · uploaded 8 Jan 2020Source
  • 1 Copy of the legal title reporttitle report.pdf · uploaded 14 Feb 2020Source
  • 2 Copy of the legal title reporttitle report.pdf · uploaded 14 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 14 Feb 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 14 Feb 2020Source
  • 1 Proforma of Allotment letterAllotment Letter format.pdf · uploaded 14 Feb 2020Source
  • 1 Declaration in FORM Bform b affidavit.pdf · uploaded 17 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_architect_gut no-94 tisgaon.pdf · uploaded 17 Feb 2020Source
  • 1 Otherpower of attorney Complete.pdf · uploaded 11 Mar 2020Source
  • 1 Disclosure of sold/ booked inventorySold Unslod Inventory till March 2022.pdf · uploaded 11 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form5 20-21.pdf · uploaded 11 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form5 21-22.pdf · uploaded 11 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)from 2 may 2020.pdf · uploaded 20 Dec 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2.pdf · uploaded 20 Dec 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q3.pdf · uploaded 20 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4.pdf · uploaded 20 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q5.pdf · uploaded 20 Dec 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q6.pdf · uploaded 20 Dec 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q7.pdf · uploaded 20 Dec 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q8.pdf · uploaded 20 Dec 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q9.pdf · uploaded 20 Dec 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q10.pdf · uploaded 20 Dec 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q11.pdf · uploaded 20 Dec 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q12.pdf · uploaded 20 Dec 2023Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q13.pdf · uploaded 20 Dec 2023Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q14.pdf · uploaded 20 Dec 2023Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q15.pdf · uploaded 20 Dec 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 may 2020.pdf · uploaded 20 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 aug 2020.pdf · uploaded 20 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2nov 2020.pdf · uploaded 20 Dec 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 feb 2021.pdf · uploaded 20 Dec 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 may 2021.pdf · uploaded 20 Dec 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 aug 2021.pdf · uploaded 20 Dec 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 nov 2021.pdf · uploaded 20 Dec 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 feb 2022.pdf · uploaded 20 Dec 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 may 2022.pdf · uploaded 20 Dec 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 aug 2022.pdf · uploaded 20 Dec 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 nov 2022.pdf · uploaded 20 Dec 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 feb 2023.pdf · uploaded 20 Dec 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)from 2 may 2023.pdf · uploaded 20 Dec 2023Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 aug 2023.pdf · uploaded 20 Dec 2023Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 nov 2023.pdf · uploaded 20 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 5 Mar 2024Source
  • 1 Declaration in FORM BForm B Affidavit.pdf · uploaded 14 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate Nov-24.pdf · uploaded 16 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Annxure D Form 3.pdf · uploaded 16 Dec 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unslod Inventory till Nov-24.pdf · uploaded 16 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Certificate Form 2.pdf · uploaded 16 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality Assurance Certificate.pdf · uploaded 16 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Annual Audit Report Form 5.pdf · uploaded 16 Dec 2024Source
  • 1 OtherClarification about delay.pdf · uploaded 17 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate March-25.pdf · uploaded 6 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate March-25.pdf · uploaded 6 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality Certificate 24-25.pdf · uploaded 6 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Unity Park form 3 March-25.pdf · uploaded 10 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Unity Park Form 5 24-25.pdf · uploaded 10 May 2025Source
  • Form 1Architech Certificate Nov-24.pdf · uploaded 18 Jul 2025Source
  • Form 2Engineer Certificate Form 2.pdf · uploaded 18 Jul 2025Source
  • Form 3Annxure D Form 3.pdf · uploaded 18 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unslod Inventory till Nov-24.pdf · uploaded 18 Jul 2025Source
  • Form 1Architect Certificate March-25.pdf · uploaded 18 Jul 2025Source
  • Form 2Engineer Certificate March-25.pdf · uploaded 18 Jul 2025Source
  • Form 3Unity Park form 31 March-25.pdf · uploaded 18 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Data March-25.pdf · uploaded 18 Jul 2025Source
  • Form 1Form 1 Unity Park June-25.pdf · uploaded 24 Jul 2025Source
  • Form 2Form 2 Engineer Certificate June-25.pdf · uploaded 24 Jul 2025Source
  • Form 3Form 3 Unity Park June 25.pdf · uploaded 24 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold-unsold inventory June-25.pdf · uploaded 24 Jul 2025Source
  • Form 5 (FY 2024-2025)Unity Park Form 5 24-25.pdf · uploaded 24 Jul 2025Source
  • Form 1Architect Certificate Sep-25.pdf · uploaded 15 Nov 2025Source
  • Form 2Engineer Certificate Sep-25.pdf · uploaded 15 Nov 2025Source
  • Form 3Form 3 Unity Park Sep-25.pdf · uploaded 15 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold & Booked Unit Sep-25.pdf · uploaded 15 Nov 2025Source
  • Form 1Architect certifiate Dec-25.pdf · uploaded 16 Jan 2026Source
  • Form 2Engineer Certificate Dec-25.pdf · uploaded 16 Jan 2026Source
  • Form 3Form 3 Unity Park Dec-25.pdf · uploaded 16 Jan 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory Dec-2025.pdf · uploaded 16 Jan 2026Source
  • Form 2A (FY 2019-2020)Form 2A.pdf · uploaded 17 Jan 2026Source
  • Form 2A (FY 2020-2021)20-21.pdf · uploaded 19 Jan 2026Source
  • Form 2A (FY 2021-2022)21-22.pdf · uploaded 19 Jan 2026Source
  • Form 2A (FY 2022-2023)22-23.pdf · uploaded 19 Jan 2026Source
  • Form 2A (FY 2023-2024)23-24.pdf · uploaded 19 Jan 2026Source
  • Form 2A (FY 2024-2025)24-25.pdf · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 1Q15.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate march-26.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 3From 3 CA Certificate march-26.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Architect Certificate June-26.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate June-26.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3Form 3 Unity Park June-26.pdf · uploaded 12 Aug 2026Source

Technical

  • Documentapproved building plan_compressed.pdf · uploaded 8 Jan 2020Source
  • DocumentLAYOUT APPROVAL.pdf · uploaded 8 Jan 2020Source

Technical (Architect)

  • DocumentArchitech Certificate Nov-24.pdf · uploaded 16 Dec 2024Source
  • DocumentArchitect Certificate March-25.pdf · uploaded 6 May 2025Source
  • DocumentForm 1 Architect Certificate June-26.pdf · uploaded 12 Aug 2026Source

Technical (Engineer)

  • DocumentEngineer Certificate March-25.pdf · uploaded 6 May 2025Source
  • DocumentForm 2 Engineer Certificate June-26.pdf · uploaded 12 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel GUT NO 94

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 4BHK45 units in all
Address
Gut No 94, Tisgaon, Near MahadaPIN 431136
Village
Tisgaon, Aurangabad taluka
Land area for this project
4,150 sq m (44,670 sq ft)
Permissible built-up area
3,068 sq m (33,024 sq ft)
Sanctioned built-up area
3,068 sq m (33,024 sq ft)
Recreational open space
415 sq m (4,467 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

GUT NO 94

Land as published on MahaRERA's project page

GUT NO 94

Boundaries

North
Road
South
Gut No 94
East
Gut No 94
West
Land Of Gut No 94 Owned By Sangita Luniya And Otrs

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking45 units

13 of 45 units booked (29%), as the promoter reported to MahaRERA

2BHK · 37 units4BHK · 8 units
BuildingTypeCarpet areaUnitsBooked
A Type Building2BHK614 sq m · 6,609 sq ft127
B Type Building2BHK390 sq m · 4,198 sq ft80
C Type Building2BHK391 sq m · 4,209 sq ft81
D Type Building2BHK470 sq m · 5,059 sq ft94
E Type Building4BHK470 sq m · 5,059 sq ft81

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBV RAUT RB and Associates—
Chartered accountantShrish Samdani—
EngineerAjay Jadhav—
OtherShaikh Junaid—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology