Skip to content
Residential / Group Housing · 2 buildings · 52 unitsRERA P52200014051

Dream City

Deedo IDDP-AHM-DPJN

Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Supa, Ahmednagar 414301 · by Abhijit Dadasaheb Pathare

Delivery3 yrs 6 mo past duePromised Apr 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 52 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 7 Nov 2017, completion promised 1 Apr 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52200014051
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P522000140517 Nov 20171 Apr 20231 Apr 2023Abhijit Dadasaheb PathareProject page
Documents59

2 documents held by Deedo, 57 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN Card.pdf · uploaded 24 Oct 2017Source

Legal

  • Legal Title reportBuilding Permission_Prant Office 1.pdf · uploaded 24 Oct 2017Source
  • Declaration Form Bnotary1.pdf · uploaded 27 Oct 2017Source
  • Legal Title reportLegal Title.pdf · uploaded 6 Nov 2024Source
  • Legal Title reportLegal Title Report.pdf · uploaded 5 Dec 2024Source
  • Other – Legal5961-Court Order.pdf · uploaded 26 Feb 2025Source
Show all 59 documentsShow fewer documents

Legal

  • Other – Legal7-12.pdf · uploaded 26 Feb 2025Source
  • Declaration Form BForm B -Revised.pdf · uploaded 25 Mar 2025Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 24 Oct 2017Source
  • 1 Copy of the legal title reportBuilding Permission_Prant Office 1.pdf · uploaded 24 Oct 2017Source
  • 1 Details of encumbrancesNon Encumbrance Certificate.pdf · uploaded 24 Oct 2017Source
  • 1 Copy of Layout Approval (in case of layout)layout plan gat no 41.pdf · uploaded 24 Oct 2017Source
  • 1 Building Plan Approval (IOD)Building Permission_Prant Office 1.pdf · uploaded 24 Oct 2017Source
  • 2 Building Plan Approval (IOD)building sanction plan 1.pdf · uploaded 24 Oct 2017Source
  • 3 Building Plan Approval (IOD)building sanction plan 2.pdf · uploaded 24 Oct 2017Source
  • 4 Building Plan Approval (IOD)building sanction plan 3.pdf · uploaded 24 Oct 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)RERA Architechs Certificate-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RERA ENGINEERS CERTIFICATE.pdf · uploaded 24 Oct 2017Source
  • 1 Proforma of Allotment letterDREAM CITY SAMPLE.pdf · uploaded 24 Oct 2017Source
  • 1 Declaration in FORM Bnotary1.pdf · uploaded 27 Oct 2017Source
  • 1 Certificates of CA (Form 3)Abhijeet pathare form 3 ca certificate final.pdf · uploaded 27 Oct 2017Source
  • 1 Copy of the legal title reportLegal Title.pdf · uploaded 6 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentSanction Letter.pdf · uploaded 6 Nov 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Deed of Declaration.pdf · uploaded 7 Nov 2024Source
  • 1 Details of encumbrancesEncumbrance Finance.pdf · uploaded 26 Nov 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 26 Nov 2024Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 26 Nov 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form I.pdf · uploaded 26 Nov 2024Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 26 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Inverntory.pdf · uploaded 26 Nov 2024View
  • 1 Declaration about Commencement CertificateDeclaration Commencement.pdf · uploaded 26 Nov 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allottment.pdf · uploaded 26 Nov 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 26 Nov 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Agreement for Sale.pdf · uploaded 26 Nov 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 26 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 26 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 26 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectFormat A.pdf · uploaded 26 Nov 2024Source
  • 2 Copy of the legal title reportLegal Title Report.pdf · uploaded 5 Dec 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 26 Feb 2025Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Feb 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 26 Feb 2025Source
  • 1 Other – Legal5961-Court Order.pdf · uploaded 26 Feb 2025Source
  • 2 Other – Legal7-12.pdf · uploaded 26 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 26 Feb 2025View
  • 1 Declaration in FORM BForm B -Revised.pdf · uploaded 25 Mar 2025Source

Technical

  • DocumentBuilding Permission_Prant Office 1.pdf · uploaded 24 Oct 2017Source
  • Documentbuilding sanction plan 1.pdf · uploaded 24 Oct 2017Source
  • Documentbuilding sanction plan 2.pdf · uploaded 24 Oct 2017Source
  • Documentbuilding sanction plan 3.pdf · uploaded 24 Oct 2017Source
  • Documentlayout plan gat no 41.pdf · uploaded 24 Oct 2017Source

Technical (Architect)

  • DocumentRERA Architechs Certificate-ilovepdf-compressed.pdf · uploaded 24 Oct 2017Source
  • DocumentForm I.pdf · uploaded 26 Nov 2024Source
  • DocumentForm 1.pdf · uploaded 26 Feb 2025Source

Technical (Engineer)

  • DocumentRERA ENGINEERS CERTIFICATE.pdf · uploaded 24 Oct 2017Source
  • DocumentForm 2.pdf · uploaded 26 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 26 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 41

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Series 1, Series 2, Series 352 units in all
Address
41PIN 414301
Village
Supa, Parner taluka
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

41

Boundaries

North
Internal Layout Road
South
Gat No 42
East
Agriculture College
West
Internal Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking52 units

0 of 52 units booked (0%), as the promoter reported to MahaRERA

1BHK · 12 units2BHK · 8 unitsSeries 1 · 4 unitsSeries 2 · 8 unitsSeries 3 · 20 units
BuildingTypeCarpet areaUnitsBooked
A Wing Phase I1BHK36.98 sq m · 398 sq ft80
A Wing Phase I1BHK37.73 sq m · 406 sq ft40
A Wing Phase I2BHK50.46 sq m · 543 sq ft40
A Wing Phase I2BHK51.58 sq m · 555 sq ft40
B Wing Phase IISeries 151.3 sq m · 552 sq ft40
B Wing Phase IISeries 251.58 sq m · 555 sq ft80
B Wing Phase IISeries 336.98 sq m · 398 sq ft200

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmol M Bhalake—
ArchitectSwapnil Shirsagar—
EngineerVivek Damodar Apate—
OtherAmir Babulal Shaikh—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology