Rahuri Mcl, Ahmednagar
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects3
Registrations3
Completion still due12 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
3 MahaRERA registrations in Rahuri Mcl
1 extended, not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Rahuri Mcl
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Ojaswini HeightsSai Bhagirathi Elite Private Limited | Due Jul 2030, extended 4 mo | — | — |
| Shri Swami Samarth HeightsNandalal Shankarlal Kasat | 2 yrs 10 mo late | — | 0% |
| Siddhivinayak ComplexUsha Prasad Tanpure | 4 yrs 6 mo late | — | 23% |
Nearby: other localities in Rahuri
Most active promoters
- Nandalal Shankarlal Kasat1 project
- Sai Bhagirathi Elite Private Limited1 project
- Usha Prasad Tanpure1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology