1 project under 1 MahaRERA registration, registered 2018–2018. 100% have a completion date extended beyond the one promised.

1RERA projects
1Registrations
0Completion still due1 past their completion date
30 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181

Projects in Pathardi(Mc)

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gulmohar Wing AYashashree DevelopersP522000148388 Jan 201831 Dec 201930 Jun 2022Extended 30 mo0