10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects7
Registrations7
Completion still due34 past their date
Median extension4 months57% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

7 MahaRERA registrations in Akola

3 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Akola

7 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sai Agastya PrideOm Sai ConstructionDue Jan 2030, extended 4 mo——
Valencia Phase ThreeShete Patil Developers AopDue Mar 2027, extended 4 mo——
Liveyoung ResidencySaisiddhi Construction1 yr 6 mo late——
Chandrabhaga ApartmentS V BUILDERS and DEVELOPERSDue Apr 2028, extended 4 mo——
ValenciaShete Patil DevelopersCompleted, extended 11 mo—33%
All 7 projects →
Akola market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Laxminivas1 project
  2. Milind Sainath Naikwadi1 project
  3. Om Sai Construction1 project
  4. Saisiddhi Construction1 project
  5. S & G Developers1 project
  6. Shete Patil Developers1 project
  7. Shete Patil Developers Aop1 project
  8. S V Builders And Developers1 project

Akola, in questions

How many projects in Akola run late?

10 in 10 MahaRERA registrations (7 of 7): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Akola by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology