Residential / Group Housing · 1 building · 474 unitsRERA P51700053843

Primrose MHADA 2

Deedo IDDP-THN-QJW3

Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 88% of its units are booked.

Usarghar, Thane 421204 · Promoter: Runwal Residency Private Limited

Delivery1 yr 7 mo past duePromised Mar 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales88% booked418 of 474 units · as the promoter reported to MahaRERA
Primrose MHADA 2 project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 1 Dec 2023, completion promised 31 Mar 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700053843
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000538431 Dec 202331 Mar 202531 Mar 2025Runwal Residency Private LimitedProject page
Documents147

1 document held by Deedo, 146 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardRunwal Residency Private Limited.pdf · uploaded 14 Sep 2023Source
  • Other – FinanceCERSAI REPORT POST QUERY.pdf · uploaded 3 Oct 2023Source

Legal

  • Legal Title reportTitle Report - primrose MHADA 2 - 20 September 2023_11zon.pdf · uploaded 20 Sep 2023Source
  • Declaration Form BFORM B -EWS compressed.pdf · uploaded 3 Oct 2023Source
  • Other – Legalpage 1-7.pdf · uploaded 20 Oct 2023Source
  • Other – Legalpage 8-15.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 16-22.pdf · uploaded 23 Nov 2023Source
Show all 147 documentsShow fewer documents

Legal

  • Other – Legalpage 23-30.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 31-37.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 38-43.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 44-49.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 50-55.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 56 -73.pdf · uploaded 23 Nov 2023Source
  • Other – Legalpage 74-95.pdf · uploaded 23 Nov 2023Source
  • Other – Legal96-119.pdf · uploaded 23 Nov 2023Source
  • Other – Legal120-143.pdf · uploaded 23 Nov 2023Source
  • Other – Legal144-167.pdf · uploaded 23 Nov 2023Source
  • Other – Legal168- 193.pdf · uploaded 23 Nov 2023Source
  • Other – Legal194-217.pdf · uploaded 23 Nov 2023Source
  • Other – Legal218-242.pdf · uploaded 23 Nov 2023Source
  • Other – Legal243 - last page.pdf · uploaded 23 Nov 2023Source
  • Other – Legal1- page 1 to 22.pdf · uploaded 23 Nov 2023Source
  • Other – Legal2-pages 23 to 36.pdf · uploaded 23 Nov 2023Source
  • Other – Legal3 page 37 - 53.pdf · uploaded 23 Nov 2023Source
  • Other – Legal4-page 54-73.pdf · uploaded 23 Nov 2023Source
  • Other – Legal5- page 74-101.pdf · uploaded 23 Nov 2023Source
  • Other – Legal6- page 102 to 127.pdf · uploaded 23 Nov 2023Source
  • Other – Legal7- page 128-153.pdf · uploaded 23 Nov 2023Source
  • Other – Legal8-page 154-179.pdf · uploaded 23 Nov 2023Source
  • Other – Legal9- page 180-205.pdf · uploaded 23 Nov 2023Source
  • Other – Legal10- page 206 - 231.pdf · uploaded 23 Nov 2023Source
  • Other – Legal11-232-257.pdf · uploaded 23 Nov 2023Source
  • Other – Legal12-258-284.pdf · uploaded 23 Nov 2023Source
  • Other – Legal13 page 285 to 290.pdf · uploaded 23 Nov 2023Source
  • Other – Legal1-page 1 to 15.pdf · uploaded 23 Nov 2023Source
  • Other – Legal2-page 16-37.pdf · uploaded 23 Nov 2023Source
  • Other – Legal3-page 38-49.pdf · uploaded 23 Nov 2023Source
  • Other – Legal4- page 50-73.pdf · uploaded 23 Nov 2023Source
  • Other – Legal5-page 74-91.pdf · uploaded 23 Nov 2023Source
  • Other – Legal6- page 92-105.pdf · uploaded 23 Nov 2023Source
  • Other – Legal7-page 106-118.pdf · uploaded 23 Nov 2023Source
  • Declaration Form BFORM B.pdf · uploaded 22 Mar 2025Source

Migrated

  • 1 PAN CardRunwal Residency Private Limited.pdf · uploaded 14 Sep 2023Source
  • 1 Copy of the legal title reportTitle Report - primrose MHADA 2 - 20 September 2023_11zon.pdf · uploaded 20 Sep 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate 22 July 2021_11zon.pdf · uploaded 21 Sep 2023Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances finance.pdf · uploaded 3 Oct 2023Source
  • 2 a Details of encumbrances concerned to FinanceLegal Encumbrances.pdf · uploaded 3 Oct 2023Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances finance.pdf · uploaded 3 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalLegal Encumbrances.pdf · uploaded 3 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)Runwal Gardens Amended Layout dated 09-05-2023 plinth parking built up area highlighted for EWS.pdf · uploaded 3 Oct 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentAmended CC WITH PLANS-58_11zon.pdf · uploaded 3 Oct 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 3 Oct 2023Source
  • 1 Declaration in FORM BFORM B -EWS compressed.pdf · uploaded 3 Oct 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 EWS 2.pdf · uploaded 3 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations - Lucy Roychoudhury (1).pdf · uploaded 3 Oct 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations Vijay Patil.pdf · uploaded 3 Oct 2023Source
  • 1 Other – FinanceCERSAI REPORT POST QUERY.pdf · uploaded 3 Oct 2023Source
  • 1 Other – TechnicalDeclaration - Allotment As per MHADA List.pdf · uploaded 3 Oct 2023Source
  • 2 Other – TechnicalDeclaration of project land (1).pdf · uploaded 3 Oct 2023Source
  • 1 Proforma of Agreement for saleRunwal Gardens AFS EWS.pdf · uploaded 4 Oct 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Agreement for sale compressed.pdf · uploaded 4 Oct 2023Source
  • 3 Other – TechnicalParking Declaration - revised on 4 October 2023.pdf · uploaded 4 Oct 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC dated - EWS 2.pdf · uploaded 12 Oct 2023Source
  • 1 Other – Legalpage 1-7.pdf · uploaded 20 Oct 2023Source
  • 2 Building Plan Approval / NA Order for plotted development42.pdf · uploaded 21 Oct 2023Source
  • 3 Building Plan Approval / NA Order for plotted development43.pdf · uploaded 21 Oct 2023Source
  • 4 Other – TechnicalAmended CC EWS LAYOUT PLINTH HIGHLIGHTED PROFORMA.pdf · uploaded 21 Oct 2023Source
  • 1 Proforma of Allotment letterAllotment Letter Final.pdf · uploaded 7 Nov 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment Letter Final.pdf · uploaded 7 Nov 2023Source
  • 3 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 16 Nov 2023Source
  • 3 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 16 Nov 2023Source
  • 1 CERSAI detailsDetails of encumbrances concerned to Finance.pdf · uploaded 16 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about seperate bank account.pdf · uploaded 16 Nov 2023Source
  • 2 Other – Legalpage 8-15.pdf · uploaded 23 Nov 2023Source
  • 3 Other – Legalpage 16-22.pdf · uploaded 23 Nov 2023Source
  • 4 Other – Legalpage 23-30.pdf · uploaded 23 Nov 2023Source
  • 5 Other – Legalpage 31-37.pdf · uploaded 23 Nov 2023Source
  • 6 Other – Legalpage 38-43.pdf · uploaded 23 Nov 2023Source
  • 7 Other – Legalpage 44-49.pdf · uploaded 23 Nov 2023Source
  • 8 Other – Legalpage 50-55.pdf · uploaded 23 Nov 2023Source
  • 9 Other – Legalpage 56 -73.pdf · uploaded 23 Nov 2023Source
  • 10 Other – Legalpage 74-95.pdf · uploaded 23 Nov 2023Source
  • 11 Other – Legal96-119.pdf · uploaded 23 Nov 2023Source
  • 12 Other – Legal120-143.pdf · uploaded 23 Nov 2023Source
  • 13 Other – Legal144-167.pdf · uploaded 23 Nov 2023Source
  • 14 Other – Legal168- 193.pdf · uploaded 23 Nov 2023Source
  • 15 Other – Legal194-217.pdf · uploaded 23 Nov 2023Source
  • 16 Other – Legal218-242.pdf · uploaded 23 Nov 2023Source
  • 17 Other – Legal243 - last page.pdf · uploaded 23 Nov 2023Source
  • 18 Other – Legal1- page 1 to 22.pdf · uploaded 23 Nov 2023Source
  • 19 Other – Legal2-pages 23 to 36.pdf · uploaded 23 Nov 2023Source
  • 20 Other – Legal3 page 37 - 53.pdf · uploaded 23 Nov 2023Source
  • 21 Other – Legal4-page 54-73.pdf · uploaded 23 Nov 2023Source
  • 22 Other – Legal5- page 74-101.pdf · uploaded 23 Nov 2023Source
  • 23 Other – Legal6- page 102 to 127.pdf · uploaded 23 Nov 2023Source
  • 24 Other – Legal7- page 128-153.pdf · uploaded 23 Nov 2023Source
  • 25 Other – Legal8-page 154-179.pdf · uploaded 23 Nov 2023Source
  • 26 Other – Legal9- page 180-205.pdf · uploaded 23 Nov 2023Source
  • 27 Other – Legal10- page 206 - 231.pdf · uploaded 23 Nov 2023Source
  • 28 Other – Legal11-232-257.pdf · uploaded 23 Nov 2023Source
  • 29 Other – Legal12-258-284.pdf · uploaded 23 Nov 2023Source
  • 30 Other – Legal13 page 285 to 290.pdf · uploaded 23 Nov 2023Source
  • 31 Other – Legal1-page 1 to 15.pdf · uploaded 23 Nov 2023Source
  • 32 Other – Legal2-page 16-37.pdf · uploaded 23 Nov 2023Source
  • 33 Other – Legal3-page 38-49.pdf · uploaded 23 Nov 2023Source
  • 34 Other – Legal4- page 50-73.pdf · uploaded 23 Nov 2023Source
  • 35 Other – Legal5-page 74-91.pdf · uploaded 23 Nov 2023Source
  • 36 Other – Legal6- page 92-105.pdf · uploaded 23 Nov 2023Source
  • 37 Other – Legal7-page 106-118.pdf · uploaded 23 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Primrose MAHADA 2.pdf · uploaded 2 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)EWS 2.pdf · uploaded 18 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 EWS.pdf · uploaded 24 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 - ews lig 2 - March 24.pdf · uploaded 2 May 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentRRPL Revised CC phase 8 dated 14 May 2024_11zon.pdf · uploaded 12 Jul 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)EWS-2 FORM 2.pdf · uploaded 18 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 EWS 2_CA.pdf · uploaded 18 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - EWS - EWS 2 -June 24.pdf · uploaded 26 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RRPL MHADA 2 Form 5.pdf · uploaded 7 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)EWS-2 RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-24.pdf · uploaded 22 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)EWS 2 Form 3 done (1).pdf · uploaded 21 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Done Form 1 EWS 2 Dec 2024.pdf · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Done EWS-2 RERA FORM 2 ENGINEERS CERTIIFICATE.pdf · uploaded 30 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Done Form 1 EWS 2 Dec 2024.pdf · uploaded 3 Feb 2025Source
  • 1 CERSAI detailsCERSAI_ PRIMROSE MHADA 2.pdf · uploaded 21 Mar 2025Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 22 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryPrimrose MHADA-1.pdf · uploaded 22 Mar 2025Source
  • 2 CERSAI detailsCERSAI_Search_Report_FINAL.pdf · uploaded 22 Mar 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A - Declaration about RERA Designated Bank Accounts -.pdf · uploaded 22 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A-EWS-2-2023-2024-1_cropped.pdf · uploaded 22 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations - Lucy Roychoudhury 24th March 2025.pdf · uploaded 24 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations - Vijay 24th March 2025.pdf · uploaded 24 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryPrimrose MHADA.pdf · uploaded 23 Apr 2025Source

Technical

  • DocumentRunwal Gardens Amended Layout dated 09-05-2023 plinth parking built up area highlighted for EWS.pdf · uploaded 3 Oct 2023Source
  • DocumentAmended CC WITH PLANS-58_11zon.pdf · uploaded 3 Oct 2023Source
  • Other – TechnicalDeclaration - Allotment As per MHADA List.pdf · uploaded 3 Oct 2023Source
  • Other – TechnicalDeclaration of project land (1).pdf · uploaded 3 Oct 2023Source
  • Other – TechnicalParking Declaration - revised on 4 October 2023.pdf · uploaded 4 Oct 2023Source
  • Document42.pdf · uploaded 21 Oct 2023Source
  • Document43.pdf · uploaded 21 Oct 2023Source
  • Other – TechnicalAmended CC EWS LAYOUT PLINTH HIGHLIGHTED PROFORMA.pdf · uploaded 21 Oct 2023Source

Technical (Architect)

  • DocumentForm 1 - EWS - EWS 2 -June 24.pdf · uploaded 2 Oct 2024Source
  • DocumentDone Form 1 EWS 2 Dec 2024.pdf · uploaded 24 Jan 2025Source
  • DocumentDone Form 1 EWS 2 Dec 2024.pdf · uploaded 3 Feb 2025Source

Technical (Engineer)

  • DocumentEWS-2 FORM 2.pdf · uploaded 2 Oct 2024Source
  • DocumentEWS-2 RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-24.pdf · uploaded 22 Oct 2024Source
  • DocumentDone EWS-2 RERA FORM 2 ENGINEERS CERTIIFICATE.pdf · uploaded 30 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSurvey No. 50 (pt)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK474 units in all
Address
Survey No. 50 (pt), Kalyan Shilphata Road, DombivaliPIN 421204
Village
Usarghar, Kalyan taluka
Designated bank account
88
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey No. 50 (pt)

Boundaries

North
Survey no 50 pt
South
Survey no 50 pt
East
Bldg EWS LIG 1
West
30 m w D P Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking474 units

418 of 474 units booked (88%), as the promoter reported to MahaRERA

1BHK · 156 units2BHK · 318 units
TypeCarpet areaUnitsBooked
1BHK27.2 sq m · 293 sq ft156130
2BHK43.74 sq m · 471 sq ft226202
2BHK43.84 sq m · 472 sq ft9286

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Sandeep Prabhu—
Chartered accountantKshirsagar and associates—
Engineerchetan sampat—
EngineerShailesh Mahimtura—
EngineerUttam Kawathankar—
OtherMahimtura Consultant Pvt Ltd—
OtherMEP consulting Engineering—
Registered real estate agentHimanshu Bhagwanji Gori—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology