Maa Gauri
Deedo IDDP-THN-SQJRCompletion was pushed back 1 year to Mar 2023, and that date has passed too; no MahaRERA orders on record; 40% of its units are booked.
Ulhasnagar (M Corp.), Thane 421004 · Promoter: Siddhivinayak Enterprise
Completion was pushed back 1 year to Mar 2023, and that date has passed too
- This projectRegistered 10 May 2021, completion promised 31 Mar 2022, revised to 31 Mar 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700029231
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700029231 | 10 May 2021 | 31 Mar 2022 | 31 Mar 2023 | Siddhivinayak Enterprise | Project page |
Documents73
2 documents held by Deedo, 71 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card.pdf · uploaded 1 Apr 2021Source
Legal
Show all 73 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 1 Apr 2021Source
- 1 Declaration in FORM BForm B Declaration.pdf · uploaded 1 Apr 2021Source
- 1 Proforma of Allotment letterLetter of Allotment.pdf · uploaded 1 Apr 2021Source
- 2 Proforma of Allotment letterAgreement Draft.pdf · uploaded 1 Apr 2021Source
- 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 5 Apr 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 5 Apr 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 5 Apr 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 5 Apr 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Certificate.pdf · uploaded 5 Apr 2021Source
- 1 Copy of the legal title reportFormat A.pdf · uploaded 1 May 2021Source
- 2 Copy of the legal title reportTitle Report.pdf · uploaded 1 May 2021Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 2 Aug 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)30-06-2021.pdf · uploaded 2 Aug 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)30-09-2021.pdf · uploaded 2 Aug 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)31-12-2021.pdf · uploaded 2 Aug 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)31-03-2022.pdf · uploaded 2 Aug 2022Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 2 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Declaration.pdf · uploaded 3 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Declaration.pdf · uploaded 3 Aug 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200243980306_For_Asset_Based_Search_04_08_2022_14_54_28_540.pdf · uploaded 4 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 22 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 2 Mar 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 2 Mar 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Certificate.pdf · uploaded 2 Mar 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 3 Mar 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 3 Mar 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 3 Mar 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 6 Mar 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 6 Mar 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Certificate.pdf · uploaded 6 Mar 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 9 Mar 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 9 Mar 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ca Certfificate.pdf · uploaded 9 Mar 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 28 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 28 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 28 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 28 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 28 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 28 Nov 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Nov 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 29 Nov 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Signed.pdf · uploaded 29 Nov 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Signed.pdf · uploaded 29 Nov 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Signed.pdf · uploaded 29 Nov 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Signed.pdf · uploaded 29 Nov 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 2 Dec 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentMAA GAURI COMPLETION CERTIFICATE.pdf · uploaded 2 Dec 2024Source
Technical (Architect)
Technical (Engineer)
- DocumentEngineer Certificate.pdf · uploaded 9 Mar 2023Source
- DocumentForm 2.pdf · uploaded 28 Nov 2024Source
- DocumentForm 2.pdf · uploaded 28 Nov 2024Source
- DocumentForm 2.pdf · uploaded 28 Nov 2024Source
- DocumentForm 2 Signed.pdf · uploaded 29 Nov 2024Source
- DocumentForm 2 Signed.pdf · uploaded 29 Nov 2024Source
- DocumentForm 2 Signed.pdf · uploaded 29 Nov 2024Source
- DocumentForm 2 Signed.pdf · uploaded 29 Nov 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsCTS NO 21022, SURVEY SHEET NO 22
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK10 units in all
- Address
- Cts No 21022, Survey Sheet No 22, Block No A 493, Room No 985, UlhasnagarPIN 421004
- Village
- Ulhasnagar (M Corp.), Ulhasnagar taluka
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Block No A 492
- South
- Sheetal Chhaya Apartment
- East
- Dashmesh Darbar
- West
- Road Village
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking10 units
4 of 10 units booked (40%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 43.98 sq m · 473 sq ft | 5 | 0 |
| 2BHK | 47.24 sq m · 508 sq ft | 5 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Prasad K Garad | — |
| Chartered accountant | Ritesh Talreja | — |
| Engineer | Darshan A Kasture | — |
Source: MahaRERA project page. Contact details are not shown.