Marathe Empire
MahaRERA shows it completed, after its date was pushed back 1 year and 6 months; no MahaRERA orders on record.
Titwala, Thane 421605 · Promoter: Saiji Builders
MahaRERA shows it completed, after its date was pushed back 1 year and 6 months
- This projectRegistered 22 Aug 2017, completion promised 30 Sep 2020, revised to 30 Mar 2022.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700009808
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700009808 | 22 Aug 2017 | 30 Sep 2020 | 30 Mar 2022 | Saiji Builders | Project page |
Documents51
25 documents held by Deedo, 26 filings listed on MahaRERA's project page
Commencement certificate (2)
Show all 51 documentsShow fewer documents
Occupancy / completion certificate (2)
Other (6)
Form 5 (5)
Document library
- Copy of the legal title reportagreement 2.pdf · uploaded 31 Jul 2017View
- Copy of Layout Approval (in case of layout)Plan 4.pdf · uploaded 31 Jul 2017View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)architec.pdf · uploaded 31 Jul 2017View
- Building Plan Approval (IOD)iod.pdf · uploaded 31 Jul 2017View
- Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 31 Jul 2017View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg.pdf · uploaded 31 Jul 2017View
- Details of encumbrancessearch report.pdf · uploaded 31 Jul 2017View
- Proforma of Allotment letteragreement with co pro.pdf · uploaded 31 Jul 2017View
- Declaration in FORM BScan.pdf · uploaded 31 Jul 2017View
- Otheragreement original.pdf · uploaded 21 Nov 2020View
- Commencement Certificates / NA Order for plotted developmentOC.pdf · uploaded 21 Nov 2020View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect certificate .pdf · uploaded 21 Jun 2021View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 21 Jun 2021View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentempire completion.pdf · uploaded 3 Jun 2023View
- Status of Formation of Legal Entity (Society/Co Op etc.)soceity empire.pdf · uploaded 3 Jun 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)2017-2018_compressed.pdf · uploaded 20 Jun 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)2018-2019_compressed.pdf · uploaded 20 Jun 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)2019-2020_compressed.pdf · uploaded 20 Jun 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)2020-2021_compressed.pdf · uploaded 20 Jun 2023View
- Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)2021-2022_compressed.pdf · uploaded 20 Jun 2023View
Promoter documents
Other legal documents
- Otheragreement original.pdfView
Proforma allotment letter
- Proforma allotment letteragreement with co pro.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals178, 181
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Address
- 181, 178PIN 421605
- Village
- Titwala, Kalyan taluka
- Location
- 19.29712, 73.21905
- Land area for this project
- 3,388 sq m (36,470 sq ft)
- Permissible built-up area
- 2,472 sq m (26,611 sq ft)
- Sanctioned built-up area
- 2,472 sq m (26,611 sq ft)
- Designated bank account
- Axis Bank
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
181,178
Boundaries
- North
- 12
- South
- 9
- East
- 0
- West
- 2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking15 parking spaces
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 15 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress2 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
Marathe Empire
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 15 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vijay Pandey And Associates | — |
| Engineer | Fakhari A Hassamwala And Associates | — |
| Other | Bhawani Construction | — |