Krishna Trident
Deedo IDDP-THN-TC4ECompletion was pushed back 4 months, to Oct 2030; no MahaRERA orders on record; 3% of its units are booked.
Tisgaon, Thane 421306 · Promoter: Sonawane Infrastructure Private Limited
Completion was pushed back 4 months, to Oct 2030
- This projectRegistered 8 Dec 2023, completion promised 28 Jun 2030, revised to 28 Oct 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Krishna Trident Tower-135 floors · 280 units5% booked
- Krishna Trident Tower-235 floors · 125 units0% booked
- Krishna Trident Tower 3 Offices and Residential8 floors · 22 units0% booked
- Krishna Trident Tower-3 Shops3 floors · 10 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700053898
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700053898 | 8 Dec 2023 | 28 Jun 2030 | 28 Oct 2030 | Sonawane Infrastructure Private Limited | Project page |
Documents118
1 document held by Deedo, 117 filings listed on MahaRERA's project page
Finance
- PAN CardSonawane Infrastructure Pvt Ltd Pancard.pdf · uploaded 7 Oct 2023Source
Legal
- Declaration Form BForm B Developer_rotated.pdf · uploaded 7 Oct 2023Source
- Other – LegalKV Index II no 1_rotated.pdf · uploaded 18 Oct 2023Source
- Other – LegalKV Index II no 2_rotated_compressed.pdf · uploaded 18 Oct 2023Source
- Other – LegalKV Index II no 3_rotated_compressed.pdf · uploaded 18 Oct 2023Source
- Other – LegalKV Index II no 4.pdf · uploaded 18 Oct 2023Source
- Legal Title reportTitle report.pdf · uploaded 18 Oct 2023Source
Show all 118 documentsShow fewer documents
Legal
- Declaration Form BForm-B.pdf · uploaded 26 Apr 2024Source
Migrated
- 1 PAN CardSonawane Infrastructure Pvt Ltd Pancard.pdf · uploaded 7 Oct 2023Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance Legal_rotated.pdf · uploaded 7 Oct 2023Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance Finance_rotated.pdf · uploaded 7 Oct 2023Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance Legal_rotated.pdf · uploaded 7 Oct 2023Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance Finance_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Copy of Layout Approval (in case of layout)Plan 01.pdf · uploaded 7 Oct 2023Source
- 2 Copy of Layout Approval (in case of layout)Plan 02.pdf · uploaded 7 Oct 2023Source
- 3 Copy of Layout Approval (in case of layout)Plan 03.pdf · uploaded 7 Oct 2023Source
- 4 Copy of Layout Approval (in case of layout)Plan 04.pdf · uploaded 7 Oct 2023Source
- 5 Copy of Layout Approval (in case of layout)Plan 05.pdf · uploaded 7 Oct 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan 02.pdf · uploaded 7 Oct 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 03.pdf · uploaded 7 Oct 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentPlan 04.pdf · uploaded 7 Oct 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentPlan 05.pdf · uploaded 7 Oct 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 7 Oct 2023Source
- 1 Declaration about Commencement CertificateFormat D_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Declaration in FORM BForm B Developer_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)KV form 1_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)KV form 2_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest in Real Estate_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Proforma of Allotment letterAllotment Letter_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Deviation Report with respect to Allotment letterDeviations of the Allotment Letter_rotated.pdf · uploaded 7 Oct 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviations for AFS_rotated.pdf · uploaded 7 Oct 2023Source
- 1 CERSAI detailsCERSAI details.pdf · uploaded 9 Oct 2023Source
- 1 Copy of the legal title reportTitle report.pdf · uploaded 18 Oct 2023Source
- 1 Proforma of Agreement for saleAFS_uploading.pdf · uploaded 18 Oct 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same1 Separate Bank Account details.pdf · uploaded 18 Oct 2023Source
- 1 Other – LegalKV Index II no 1_rotated.pdf · uploaded 18 Oct 2023Source
- 2 Other – LegalKV Index II no 2_rotated_compressed.pdf · uploaded 18 Oct 2023Source
- 3 Other – LegalKV Index II no 3_rotated_compressed.pdf · uploaded 18 Oct 2023Source
- 4 Other – LegalKV Index II no 4.pdf · uploaded 18 Oct 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval.pdf · uploaded 3 Nov 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate final 241123.pdf · uploaded 24 Nov 2023Source
- 3 a Details of encumbrances concerned to FinanceEncumbrance Letter.pdf · uploaded 23 Apr 2024Source
- 3 b Details of encumbrances concerned to LegalEncumbrance Letter.pdf · uploaded 23 Apr 2024Source
- 2 Declaration in FORM BForm-B.pdf · uploaded 26 Apr 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)SIPL-ARCHITECT CERTIFICATE.pdf · uploaded 10 May 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)SIPL-ENGINEERS CERTIFICATE.pdf · uploaded 10 May 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SIPL-CA-CERTIFICATE.pdf · uploaded 10 May 2024Source
- 6 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 1.pdf · uploaded 24 Jun 2024Source
- 7 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 2.pdf · uploaded 24 Jun 2024Source
- 8 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 3.pdf · uploaded 24 Jun 2024Source
- 9 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 4.pdf · uploaded 24 Jun 2024Source
- 10 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 5.pdf · uploaded 24 Jun 2024Source
- 11 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN 6.pdf · uploaded 24 Jun 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentRevise CC Trident.pdf · uploaded 24 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)sipl from-1.pdf · uploaded 24 Jul 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)sipl from-2.pdf · uploaded 24 Jul 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)sipl from-3 (1).pdf · uploaded 24 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Trident 23-24.pdf · uploaded 19 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Trident 23-24.pdf · uploaded 19 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Trident Dec 24.pdf · uploaded 28 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Trident Dec 24_compressed.pdf · uploaded 28 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Tridend Dec 24.pdf · uploaded 28 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDesclosure od Sold Unsold Inventory Trident_compressed.pdf · uploaded 29 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Trident (2).pdf · uploaded 29 Jan 2025Source
- 1 Proforma of Agreement for saleAgreement For Sale-Krishna Trident.pdf · uploaded 24 Jun 2025Source
- Form 5 (FY 2024-2025)Form 5 KT (24-25).pdf · uploaded 21 Nov 2025Source
- Withdrawal Update Form 1Form 1 Trident.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1sipl architect second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1sipl architect second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1sipl architect second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1sipl architect second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 2Form 2 Trident.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 2sipl engineer second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 2sipl engineer second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 2sipl engineer second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 2sipl engineer second qtr 25-26.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 3Form 3 Trident (1).pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 3Form 3 Trident (1).pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 3Form 3 Trident (1).pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 3sipl - ca certificte second qtr 25-26 (1).pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 3sipl - ca certificte second qtr 25-26 (1).pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1sipl architect certificate third qtr 26-26.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 2sipl- engineer certificate third qtr 25-26.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 3sipl ca certificate third qtr 25- 26.pdf · uploaded 27 Jan 2026Source
- Withdrawal Update Form 1sipl architect certificate third qtr 26-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 1architect certificate sipl - forth qtr 25-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 1architect certificate sipl - forth qtr 25-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 2sipl- engineer certificate third qtr 25-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 2engineer certificate sipl - forth qtr 25-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 2engineer certificate sipl - forth qtr 25-26.pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 3CA CERTICATE - SIPL-QTR-1- 2026-27 (1).pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 3ca certificate update - sipl - forth qtr 25-26 (3).pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 3ca certificate update - sipl - forth qtr 25-26 (3).pdf · uploaded 31 Jul 2026Source
- Withdrawal Update Form 1ARCHITECT - SIPL-QTR-1- 2026-27.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 2ENGINEERS CERTICATE - SIPL-QTR-1- 2026-27.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 3Ca Form 3 june 26_compressed.pdf · uploaded 25 Aug 2026Source
Technical
- DocumentPlan 01.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 02.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 03.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 04.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 05.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 02.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 03.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 04.pdf · uploaded 7 Oct 2023Source
- DocumentPlan 05.pdf · uploaded 7 Oct 2023Source
- DocumentREVISED SANCTION PLAN 1.pdf · uploaded 24 Jun 2024Source
- DocumentREVISED SANCTION PLAN 2.pdf · uploaded 24 Jun 2024Source
- DocumentREVISED SANCTION PLAN 3.pdf · uploaded 24 Jun 2024Source
- DocumentREVISED SANCTION PLAN 4.pdf · uploaded 24 Jun 2024Source
- DocumentREVISED SANCTION PLAN 5.pdf · uploaded 24 Jun 2024Source
- DocumentKrishna Trident Revise Plan.pdf · uploaded 24 Aug 2026Source
- DocumentKrishna Trident Revise Plan highlighted.pdf · uploaded 23 Sep 2026Source
- DocumentKrishna Trident Revise Plan highlighted.pdf · uploaded 23 Sep 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals100 Feet Road, 2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop437 units in all
- Address
- S. No. 41, H. No. 1, 2, 3, and S. No. 42, H. No. 6 and 7A, 100 Feet Road, Tisgoan, Shri Malang Road, Kalyan East 421306, 100 Feet Road, Shri Malang Road, Tisgoan, Kalyan EastPIN 421306
- Village
- Tisgaon, Kalyan taluka
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Mauje Nandivali Shiv
- South
- S No 42 H No 5 Property by Dhyaneshwar Gaikwad
- East
- Survey No 41
- West
- S No 42 H No 8 Property by Sukrya Gaikwad
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking437 units
15 of 437 units booked (3%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Krishna Trident Tower-1 | 1BHK | 38.09 sq m · 410 sq ft | 140 | 3 |
| Krishna Trident Tower-1 | 1BHK | 39.95 sq m · 430 sq ft | 70 | 1 |
| Krishna Trident Tower-1 | 2BHK | 52.03 sq m · 560 sq ft | 70 | 11 |
| Krishna Trident Tower-2 | 1BHK | 38.09 sq m · 410 sq ft | 61 | 0 |
| Krishna Trident Tower-2 | 1BHK | 39.95 sq m · 430 sq ft | 32 | 0 |
| Krishna Trident Tower-2 | 2BHK | 52.03 sq m · 560 sq ft | 32 | 0 |
| Krishna Trident Tower 3 Offices and Residential | 1BHK | 38.09 sq m · 410 sq ft | 8 | 0 |
| Krishna Trident Tower 3 Offices and Residential | 1BHK | 39.95 sq m · 430 sq ft | 2 | 0 |
Show all 22 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Krishna Trident Tower 3 Offices and Residential | 2BHK | 52.03 sq m · 560 sq ft | 2 | 0 |
| Krishna Trident Tower 3 Offices and Residential | Office space | 33.72 sq m · 363 sq ft | 2 | 0 |
| Krishna Trident Tower 3 Offices and Residential | Office space | 35.52 sq m · 382 sq ft | 2 | 0 |
| Krishna Trident Tower 3 Offices and Residential | Office space | 46.17 sq m · 497 sq ft | 2 | 0 |
| Krishna Trident Tower 3 Offices and Residential | Office space | 47.57 sq m · 512 sq ft | 2 | 0 |
| Krishna Trident Tower 3 Offices and Residential | Office space | 49.7 sq m · 535 sq ft | 2 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 15.79 sq m · 170 sq ft | 1 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 16.44 sq m · 177 sq ft | 1 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 19.14 sq m · 206 sq ft | 1 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 20.16 sq m · 217 sq ft | 1 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 23.78 sq m · 256 sq ft | 2 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 29.26 sq m · 315 sq ft | 2 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 30.56 sq m · 329 sq ft | 1 | 0 |
| Krishna Trident Tower-3 Shops | Shop | 41.81 sq m · 450 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nikhil Ashok Borade | — |
| Chartered accountant | CA Darshan Pankaj Thakkar | — |
| Chartered accountant | Pooja V Jain & Co | — |
| Engineer | Pradnya Ashok Ahire | — |
| Engineer | Sandeep Khandode | — |
| Other | Kalpesh Wadiya | — |
Source: MahaRERA project page. Contact details are not shown.