Tarabaug
Deedo IDDP-THN-RXMZIts promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Thane (M Corp.), Thane 400602 · Promoter: Vidyadhar Achyut Vaishampayan
Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 2 Feb 2022, completion promised 20 Dec 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700032881
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700032881 | 2 Feb 2022 | 20 Dec 2024 | 20 Dec 2024 | Vidyadhar Achyut Vaishampayan | Project page |
Documents42
1 document held by Deedo, 41 filings listed on MahaRERA's project page
Finance
- PAN CardPromoter-PANandAadhar.pdf · uploaded 13 Jan 2022Source
Legal
Show all 42 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 13 Jan 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentTarabaug-Commencement Certificate.pdf · uploaded 13 Jan 2022Source
- 1 Declaration about Commencement CertificateSHREE ENT-RERA- FORM-D.pdf · uploaded 13 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Tarabaug-Architect Certificate.pdf · uploaded 13 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Tarabaug-Engineers Certificate.pdf · uploaded 13 Jan 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHREE ENT-RERA- FORM 3-Registration.pdf · uploaded 13 Jan 2022Source
- 1 Proforma of Allotment letterTarabaug-Flat Sale Agreement and Letter of Allotment.pdf · uploaded 13 Jan 2022Source
- 1 CERSAI detailsTarabaug-Undertaking-CersaiDetails.pdf · uploaded 19 Jan 2022Source
- 1 Copy of the legal title reportShreeEnt-Legal Title Report-25012022_compressed.pdf · uploaded 25 Jan 2022Source
- 1 Declaration in FORM BShree Ent-Form B-25012022.pdf · uploaded 25 Jan 2022Source
- 1 OtherShree Ent-Response Letter- 25012022.pdf · uploaded 25 Jan 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)SHREE ENETERPRISES - ENGINEER CERTIFICATE - MAR-22.pdf · uploaded 20 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)04 FORM 1 - Architect's Certificate JUNE 2022.pdf · uploaded 20 Mar 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)05 FORM 1 - Architect's Certificate SEPT 2022.pdf · uploaded 20 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)UDIN - FORM-5 - FY 2021-22.pdf · uploaded 20 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)UDIN - FORM-5 - FY 2022-23.pdf · uploaded 20 Mar 2024Source
- 1 Proforma of Agreement for saleProforma - Agreement for Sale.pdf · uploaded 20 Mar 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentTarabaug-Occupancy Certificate.pdf · uploaded 20 Mar 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form-4 - Architect Certificate.pdf · uploaded 20 Mar 2024Source
- 2 a Details of encumbrances concerned to FinanceShree Enterprises - Declaration of No Charge Or Encumbrance.pdf · uploaded 27 Mar 2024Source
- 1 b Details of encumbrances concerned to LegalShree Enterprises - Declaration of No Charge Or Encumbrance.pdf · uploaded 27 Mar 2024Source
- 1 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 31-03-2022.pdf · uploaded 27 Mar 2024Source
- 2 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 30-06-2022.pdf · uploaded 27 Mar 2024Source
- 3 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 30-09-2022.pdf · uploaded 27 Mar 2024Source
- 4 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 31-12-2022.pdf · uploaded 27 Mar 2024Source
- 5 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 31-03-2023.pdf · uploaded 27 Mar 2024Source
- 6 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 30-06-2023.pdf · uploaded 27 Mar 2024Source
- 7 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 30-09-2023.pdf · uploaded 27 Mar 2024Source
- 8 Disclosure of sold/ booked inventoryShree Enterprises - Disclosure of Inventory as on 31-12-2023.pdf · uploaded 27 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameShree Enterprises - Declaration about Separate Bank Account.pdf · uploaded 27 Mar 2024Source
Technical
Technical (Architect)
- DocumentTarabaug-Architect Certificate.pdf · uploaded 13 Jan 2022Source
Technical (Engineer)
- DocumentTarabaug-Engineers Certificate.pdf · uploaded 13 Jan 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals1A OF TIKA NO. 21, CTS 114. 7A
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1RK, 2BHK, 3BHK21 units in all
- Address
- Cts 114. 7a, 1a Of Tika No. 21, Off. Gokhale Road, Prashant Nagar, NaupadaPIN 400602
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.19028, 72.97115
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Access And Cts 1a
- South
- Cts 116
- East
- Open Land And Cts 1a
- West
- Prashant Nagar Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking21 units
0 of 21 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 26.01 sq m · 280 sq ft | 1 | 0 |
| 1RK | 26.85 sq m · 289 sq ft | 1 | 0 |
| 1RK | 26.85 sq m · 289 sq ft | 1 | 0 |
| 2BHK | 61.78 sq m · 665 sq ft | 1 | 0 |
| 2BHK | 63.27 sq m · 681 sq ft | 1 | 0 |
| 2BHK | 63.55 sq m · 684 sq ft | 1 | 0 |
| 2BHK | 66.24 sq m · 713 sq ft | 1 | 0 |
| 2BHK | 129.12 sq m · 1,390 sq ft | 2 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 193.71 sq m · 2,085 sq ft | 3 | 0 |
| 2BHK | 246 sq m · 2,648 sq ft | 4 | 0 |
| 2BHK | 247.48 sq m · 2,664 sq ft | 4 | 0 |
| 3BHK | 97.73 sq m · 1,052 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Jitendra Mukadam On Behalf Of Godbole Mukadam & Associates | — |
| Chartered accountant | Renukadas Dande On Behalf Of Renukadas And Company | — |
| Engineer | Anand Sawant On Behalf Of Pentacon Structural Consultants Private Limited | — |
Source: MahaRERA project page. Contact details are not shown.