Psk Skylar
Completion was pushed back 4 years, to Dec 2027; no MahaRERA orders on record; 12% of its units are booked.
Thane (M Corp.), Thane 400615 · Promoter: Gururaj Developers
Completion was pushed back 4 years, to Dec 2027
- This projectRegistered 3 May 2018, completion promised 30 Dec 2023, revised to 31 Dec 2027.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700016320
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700016320 | 3 May 2018 | 30 Dec 2023 | 31 Dec 2027 | Gururaj Developers | Project page |
Documents55
2 documents held by Deedo, 53 filings listed on MahaRERA's project page
Finance
- PAN CardPancard.pdf · uploaded 25 Apr 2018Source
Legal
Show all 55 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 25 Apr 2018Source
- 1 Building Plan Approval (IOD)IOD.pdf · uploaded 25 Apr 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 25 Apr 2018Source
- 1 Declaration in FORM BForm B.pdf · uploaded 25 Apr 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 25 Apr 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate.pdf · uploaded 25 Apr 2018Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 25 Apr 2018Source
- 1 Proforma of Allotment letterRera Agr for sale.pdf · uploaded 25 Apr 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 (1).pdf · uploaded 8 Jul 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 8 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 8 Jul 2024Source
- 1 CERSAI detailsUndertaking for No Cersai Report.pdf · uploaded 8 Jul 2024Source
- 1 Disclosure of sold/ booked inventoryDiscloser of Sold units.pdf · uploaded 8 Jul 2024Source
- 2 Certificates of CA (Form 3)Gururaj Developers-Form-3.pdf · uploaded 8 Jul 2024Source
- 3 Certificates of CA (Form 3)20240619024923.pdf · uploaded 8 Jul 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure -disclosure in other entities.pdf · uploaded 8 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 (1).pdf · uploaded 8 Jul 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format -A seperte bank declaration.pdf · uploaded 8 Jul 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 20 Jan 2025Source
- Withdrawal Update Form 1Form - 1_Q1_GD.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 1Form - 1_Q1_GD.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 2GD_Form-2_Q1.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 2GD_Form-2_Q1.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 3GD_Form 3_Q1.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 3GD_Form 3_Q1.pdf · uploaded 1 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q2 GD.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 2GD_Form-2_Q2.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 3Signed CA Certificate GURURAJ_sept 25.pdf · uploaded 4 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q3 GD.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 2GD_Form-2_Q3.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 3GD_Form 3_Q3.pdf · uploaded 5 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q4 GD.pdf · uploaded 6 Jun 2026Source
- Withdrawal Update Form 2Form 2 Q4.pdf · uploaded 6 Jun 2026Source
- Withdrawal Update Form 3GD Form 3 Q4.pdf · uploaded 6 Jun 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals113/16, 117/3B
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop145 units in all
- Address
- 118, 113/16, 117/3B, 117/3C, 117/3D, Village Owale, Anand NagarPIN 400615
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.26508, 72.96793
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot Survey No 87 3part
- South
- 40 mtr DP Road
- East
- Plot New Survey No 115
- West
- Ghodbunder Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking145 units
18 of 145 units booked (12%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.95 sq m · 430 sq ft | 39 | 4 |
| 1BHK | 40.23 sq m · 433 sq ft | 26 | 0 |
| 2BHK | 58.06 sq m · 625 sq ft | 13 | 3 |
| 2BHK | 60.39 sq m · 650 sq ft | 13 | 5 |
| Office space | 22.3 sq m · 240 sq ft | 6 | 0 |
| Office space | 38.09 sq m · 410 sq ft | 6 | 0 |
| Office space | 38.55 sq m · 415 sq ft | 6 | 0 |
| Office space | 43.66 sq m · 470 sq ft | 6 | 0 |
Show all 18 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 47.38 sq m · 510 sq ft | 6 | 1 |
| Office space | 52.03 sq m · 560 sq ft | 6 | 0 |
| Office space | 57.14 sq m · 615 sq ft | 6 | 0 |
| Office space | 307.04 sq m · 3,305 sq ft | 6 | 0 |
| Office space | 349.32 sq m · 3,760 sq ft | 1 | 0 |
| Shop | 68.75 sq m · 740 sq ft | 1 | 1 |
| Shop | 81.75 sq m · 880 sq ft | 1 | 1 |
| Shop | 96.15 sq m · 1,035 sq ft | 1 | 1 |
| Shop | 150.04 sq m · 1,615 sq ft | 1 | 1 |
| Shop | 156.08 sq m · 1,680 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Nehali Dhaval Doshi | — |
| Chartered accountant | V.B. Waghmare & Co. | — |
| Chartered accountant | V.V. Bhate & Co. | — |
Source: MahaRERA project page. Contact details are not shown.