Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Thane (M Corp.), Thane 400602 · Promoter: Dura Vida Associates
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 10 May 2022, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700035133
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700035133 | 10 May 2022 | 30 Jun 2025 | 30 Jun 2025 | Dura Vida Associates | Project page |
Documents70
1 document held by Deedo, 69 filings listed on MahaRERA's project page
Finance
Show all 70 documentsShow fewer documents
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 19 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RCC.pdf · uploaded 19 Apr 2022Source
- 1 Proforma of Allotment letterSample agreement.pdf · uploaded 19 Apr 2022Source
- 1 Declaration about Commencement CertificateForm D.pdf · uploaded 21 Apr 2022Source
- 1 Status of ConveyanceAgreement for Sale.pdf · uploaded 21 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 27 Apr 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding plan.pdf · uploaded 27 Apr 2022Source
- 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 29 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 29 Apr 2022Source
- 1 CERSAI detailsCERSAI CERTIFICATE - ASSET BASED.pdf · uploaded 6 May 2022Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD BOOKED INVENTORY.pdf · uploaded 19 May 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentAmended Plan 2.pdf · uploaded 15 Oct 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentAmended Plan 2.pdf · uploaded 15 Oct 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentAmended Plan 3.pdf · uploaded 15 Oct 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentAmended Plan 4.pdf · uploaded 15 Oct 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentREVISED CC.pdf · uploaded 15 Oct 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 271022.pdf · uploaded 28 Oct 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 05112022.pdf · uploaded 9 Nov 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)NIL decalration 1920 2021.pdf · uploaded 9 Nov 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)NIL decalration 1920 2021.pdf · uploaded 9 Nov 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)From 2A 05112022.pdf · uploaded 9 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)NIL decalration 1920 2021.pdf · uploaded 9 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)NIL decalration 1920 2021.pdf · uploaded 9 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)NIL decalration 1920 2021.pdf · uploaded 9 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2021.pdf · uploaded 9 Nov 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)From 5 2122.pdf · uploaded 9 Nov 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM - 3.pdf · uploaded 12 Dec 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 5.pdf · uploaded 18 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Feb 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 18 Feb 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentAmended Plan 1.pdf · uploaded 22 May 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentAmended Plan 2.pdf · uploaded 22 May 2023Source
- 8 Building Plan Approval / NA Order for plotted developmentAmended Plan 3.pdf · uploaded 22 May 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentAmended CC 120523.pdf · uploaded 22 May 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2 160523.pdf · uploaded 22 May 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 A 160523.pdf · uploaded 22 May 2023Source
- 1 Other – TechnicalArchitect Certificate 250423.pdf · uploaded 22 May 2023Source
- 1 Other – FinanceForm 5.pdf · uploaded 24 May 2023Source
- 2 Other – FinanceForm 5 Q4.pdf · uploaded 24 May 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 15 Feb 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)RCC.pdf · uploaded 15 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 5.pdf · uploaded 15 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 2324.pdf · uploaded 18 May 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 2324.pdf · uploaded 18 May 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 5 2324.pdf · uploaded 18 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Annual 5 2324.pdf · uploaded 18 May 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Ground to 6 th floor.pdf · uploaded 18 Nov 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Terrace and 7 th floor.pdf · uploaded 18 Nov 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Ground to 6 th floor.pdf · uploaded 18 Nov 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Terrace and 7 th floor.pdf · uploaded 18 Nov 2024Source
Technical
- DocumentLayout.pdf · uploaded 27 Apr 2022Source
- DocumentBuilding plan.pdf · uploaded 27 Apr 2022Source
- DocumentAmended Plan 2.pdf · uploaded 15 Oct 2022Source
- DocumentAmended Plan 2.pdf · uploaded 15 Oct 2022Source
- DocumentAmended Plan 3.pdf · uploaded 15 Oct 2022Source
- DocumentAmended Plan 4.pdf · uploaded 15 Oct 2022Source
- DocumentAmended Plan 1.pdf · uploaded 22 May 2023Source
- DocumentAmended Plan 2.pdf · uploaded 22 May 2023Source
- DocumentAmended Plan 3.pdf · uploaded 22 May 2023Source
- Other – TechnicalArchitect Certificate 250423.pdf · uploaded 22 May 2023Source
Technical (Architect)
- Documentform 1 2324.pdf · uploaded 18 May 2024Source
Technical (Engineer)
- Documentform 2 2324.pdf · uploaded 18 May 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals77 TIKA NO 18 NAUPADA
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK, 5BHK & more, Shop16 units in all
- Address
- 77 Tika No 18 Naupada, L B S Marg, NaupadaPIN 400602
- Village
- Thane (M Corp.), Thane taluka
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Giri Heven Chs Ltd
- South
- Giri Raj Chs
- East
- Giri Raj Gate
- West
- Jvm Corner Stone Building
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
0 of 16 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 127.74 sq m · 1,375 sq ft | 3 | 0 |
| 3BHK | 133.91 sq m · 1,441 sq ft | 4 | 0 |
| 5BHK & more | 253.34 sq m · 2,727 sq ft | 1 | 0 |
| 5BHK & more | 262.69 sq m · 2,828 sq ft | 1 | 0 |
| Shop | 9.18 sq m · 99 sq ft | 1 | 0 |
| Shop | 11.39 sq m · 123 sq ft | 1 | 0 |
| Shop | 11.78 sq m · 127 sq ft | 1 | 0 |
| Shop | 13.05 sq m · 140 sq ft | 1 | 0 |
Show all 11 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 13.67 sq m · 147 sq ft | 1 | 0 |
| Shop | 14.6 sq m · 157 sq ft | 1 | 0 |
| Shop | 16.15 sq m · 174 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ten Folds | — |
| Chartered accountant | Milind Madhukar Dnyate | — |
| Chartered accountant | Pravin Kothari Nemichand Kothari | — |
| Engineer | Ajay Mahale | — |
Source: MahaRERA project page. Contact details are not shown.