Extended 12 mo9 floorsRERA P51700030923
Main building, Dattavihar
Deedo IDDP-THN-D1KJ-DATTAVMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked77%43 of 56 · MahaRERA
Completion31 Mar 202531 Mar 2024 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29 m² (312 sq.ft) | 3 | 3 |
| 1BHK | 36.5 m² (393 sq.ft) | 1 | 1 |
| 1BHK | 41.3 m² (444 sq.ft) | 5 | 3 |
| 1BHK | 41.6 m² (448 sq.ft) | 8 | 5 |
| 1BHK-Existing Owners | 36.5 m² (393 sq.ft) | 2 | 2 |
| 1RK | 21.1 m² (227 sq.ft) | 2 | 2 |
| 1RK-Existing Owners | 21.1 m² (227 sq.ft) | 3 | 3 |
| 2BHK | 58.1 m² (625 sq.ft) | 1 | 0 |
| 2BHK | 60.4 m² (650 sq.ft) | 1 | 0 |
| 2BHK | 62.6 m² (674 sq.ft) | 8 | 4 |
| 2BHK | 68.9 m² (742 sq.ft) | 3 | 1 |
| 2BHK-Existing Owners | 58.1 m² (625 sq.ft) | 4 | 4 |
| 2BHK-Existing Owners | 60.4 m² (650 sq.ft) | 7 | 7 |
| 2BHK-Existing Owners | 64.5 m² (695 sq.ft) | 3 | 3 |
| 2BHK-Existing Owners | 68.9 m² (742 sq.ft) | 5 | 5 |
As registered with MahaRERA
- RERA registration
- P51700030923 · registered 29 Sep 2021
- Promised completion
- 31 Mar 2024
- Revised completion
- 31 Mar 2025
- Sanctioned habitable floors
- 9
- Building
- DATTAVIHAR
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- Deedo IDDP-THN-D1KJ-DATTAV
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Mar 2024, revised to 31 Mar 2025.
How many floors does Main building have?
9 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology