Extended 4 mo17 floors · 62 flatsRERA P51700022870
Main building, Aurum
Deedo IDDP-THN-G6PW-AURUM18 flats have a sale on record, 2 are booked without a sale deed yet and 19 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Median saleNot on recordneeds 3 or more sales
Booked32%20 of 62 · Oct 2026
Completion15 Jan 202715 Sep 2026 · revised
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Booked, no deed yet
- Unsold
- Reserved, rehab or other
01020304
Fl 17
Fl 16
Fl 15
Fl 14
Fl 13
Fl 12
Fl 11
Fl 10
Fl 9
Fl 8
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
Fl G
2 BHK2 BHK2 BHK
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedUnsold
Flat 1604
2 BHK · 790 sq ft · floor 16
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 63.1 m² (679 sq.ft) | 19 | 0 |
| 2BHK | 68.8 m² (741 sq.ft) | 19 | 3 |
| 2BHK | 73.3 m² (789 sq.ft) | 3 | 0 |
| 2BHK | 73.4 m² (790 sq.ft) | 3 | 0 |
| 2BHK | 74.9 m² (806 sq.ft) | 3 | 1 |
| 2BHK | 74.9 m² (806 sq.ft) | 3 | 0 |
| 2BHK | 78.9 m² (849 sq.ft) | 4 | 0 |
| 2BHK | 80.8 m² (870 sq.ft) | 6 | 0 |
| 4BHK | 132.9 m² (1,431 sq.ft) | 1 | 0 |
| Shop | 98.8 m² (1,064 sq.ft) | 1 | 0 |
| Shop | 99.3 m² (1,069 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700022870 · registered 1 Nov 2019
- Promised completion
- 15 Sep 2026
- Revised completion
- 15 Jan 2027
- Sanctioned habitable floors
- 17
- Building
- AURUM
- Sanctioned floors (incl. basement, stilt, podium)
- 17
- Units declared
- 63
- Homes
- 61
- Shops and offices
- 2
- Sanctioned FSI area (sq m)
- 16
- MahaRERA status
- Certificate Signed
- Deedo ID
- Deedo IDDP-THN-G6PW-AURUM
Questions about Main building
How many flats in Main building are sold?
18 flats have a sale on record, 2 are booked without a sale deed yet and 19 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 15 Sep 2026, revised to 15 Jan 2027.
How many floors does Main building have?
17 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology