Bhumiraj Hills
Completion due Dec 2027Navi Mumbai (M Corp.), Thane 400614 |Promoter: Bhumiraj Builders Pvt.ltd., Bhumiraj Builders Pvt. Ltd.
Project summary
As registered with MahaRERA
- RERA registrations
- 4
- Phases
- 1
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 years and 1 month
P51700016926- Registered
- 22 Jun 2018
- Promised
- 30 Nov 2023
- Revised
- 31 Dec 2027
Completion pushed back 4 years and 1 month
P51700017034- Registered
- 4 Jul 2018
- Promised
- 30 Nov 2023
- Revised
- 31 Dec 2027
Completion pushed back 4 years and 1 month
P51700017140- Registered
- 16 Jul 2018
- Promised
- 30 Nov 2023
- Revised
- 31 Dec 2027
Completion pushed back 3 years and 4 months
P51700019655- Registered
- 20 Feb 2019
- Promised
- 29 Aug 2024
- Revised
- 31 Dec 2027
4 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700016926 | 22 Jun 2018 | 30 Nov 2023 | 31 Dec 2027 | Bhumiraj Builders Pvt.ltd. | Project page |
| P51700017034 | 4 Jul 2018 | 30 Nov 2023 | 31 Dec 2027 | Bhumiraj Builders Pvt. Ltd. | Project page |
| P51700017140 | 16 Jul 2018 | 30 Nov 2023 | 31 Dec 2027 | Bhumiraj Builders Pvt. Ltd. | Project page |
| P51700019655 | 20 Feb 2019 | 29 Aug 2024 | 31 Dec 2027 | Bhumiraj Builders Pvt. Ltd. | Project page |
Documents
8 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order13 Mar 2024Matched by RERA number
Regulatory order: PROJECT NAME:BHUMIRAJ HILLS TOWER 4(Regulatory Case No. 177 of 2024) dated 13 March 2024.
- Regulatory order13 Mar 2024Matched by RERA number
Regulatory order: PROJECT NAME:BHUMIRAJ HILLS TOWER 2 & 3(Regulatory Case No. 176 of 2024) dated 13 March 2024.
- Regulatory order13 Mar 2024Matched by RERA number
Regulatory order: PROJECT NAME:BHUMIRAJ HILLS TOWER 1(Regulatory Case No. 175 of 2024) dated 13 March 2024.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Navi Mumbai (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.