Registration
RERA numbers
PromoterBhumiraj Builders Pvt. Ltd., Bhumiraj Builders Pvt.ltd.
Status on MahaRERACertificate Signed
Registered on22 Jun 2018
Delivery
Promised completion29 Aug 2024
Revised completion31 Dec 2027
Delay vs RERA date+3 years and 4 monthsrevised completion date
Extension certificates4
Size
Project land area—
Buildings on record5
Units197
Units booked116% of units
Regulatory
MahaRERA cases3Regulatory order (3)
Documents on file8
Last checked on MahaRERA13 Oct 2026

Add a project

Search by project name, RERA number or building.

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pagesDelay counts months from the completion date promised at registration.Methodology