Building No 1 · DB Ozone

Mirabhayandar (M Corp.) · RERA P51700003433

IDBLD_07133424 floorsExtended 60 mo
24Sanctioned habitable floorsregistration certificate
30 Dec 2024Revised completionpromised 31 Dec 2019
146 of 146Units bookedMahaRERA project page

Floors

24 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700003433 · registered 5 Aug 2017
Promised completion
31 Dec 2019
Revised completion
30 Dec 2024
Sanctioned habitable floors
24
ProjectId
8,461
ProjectName
DB Ozone
TotalUnitCount
0
ProjectBuildingId
4,894
BuildingNameNumber
Building No 1
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P51700003433
ProjectBuildingWingsId
4,894
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Building No 1
NoOfBuildingWingFloorProposed
24
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
24

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
B1 X01 EVEN 1.5BHK45.4 m² (488 sq.ft)99
B1 X01 ODD 1.5BHK45.2 m² (487 sq.ft)1010
B1 X02 EVEN 2BHK51.7 m² (557 sq.ft)2727
B1 X02 ODD 2BHK52.1 m² (560 sq.ft)3030
B1 X03 EVEN 1BHK33.6 m² (362 sq.ft)3030
B1 X03 ODD 1BHK33.4 m² (360 sq.ft)4040
Total146146
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology