Fennel

Deedo IDDP-THN-G6Z4

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 77% of its units are booked.

Kalambhe, Thane 421601 · Promoter: Royale Urbanspace LLP

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales77% booked213 of 276 units · as the promoter reported to MahaRERA
Fennel project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • P51700003652Registered 6 Aug 2017, completion promised 30 Dec 2023, and still not shown completed today.
  • P51700005481Registered 11 Aug 2017, completion promised 31 Dec 2019, and still not shown completed today.
  • P51700013833Registered 27 Oct 2017, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

3 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations3
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000036526 Aug 201730 Dec 202330 Dec 2023Royale Urbanspace LLPProject page
P5170000548111 Aug 201731 Dec 201931 Dec 2019Royale Urbanspace LLPProject page
P5170001383327 Oct 201731 Dec 202630 Apr 2027Royale Urbanspace LLPProject page
Documents167

3 documents held by Deedo, 164 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP51700005481 · 11 Aug 2017ViewSource
  • Registration certificateP51700003652 · 9 Sep 2021ViewSource
  • Registration certificateP51700013833 · 14 Aug 2026ViewSource

Finance

  • PAN CardP51700003652 · pan card of Royale Urbanspace LLP 001.pdf · uploaded 21 Jul 2017Source
  • PAN CardP51700013833 · pan card of Royale Urbanspace LLP 001.pdf · uploaded 21 Jul 2017Source
  • PAN CardP51700005481 · LLP Pan Card.pdf · uploaded 31 Jul 2017Source

Legal

  • Legal Title reportP51700003652 · Title Report.pdf · uploaded 31 Jul 2017Source
  • Declaration Form BP51700003652 · Final New (H-Type).pdf · uploaded 31 Jul 2017Source
Show all 167 documentsShow fewer documents

Legal

  • Declaration Form BP51700005481 · FENNEL 'D'.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportP51700005481 · Title Report.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportP51700013833 · TITLE REPORT.pdf · uploaded 1 Aug 2017Source
  • Declaration Form BP51700013833 · Form - B (G Bldg) new.pdf · uploaded 23 Oct 2017Source
  • OtherP51700003652 · H RERA.pdf · uploaded 20 Apr 2019Source
  • OtherP51700003652 · H RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • OtherP51700005481 · D RERA.pdf · uploaded 20 Apr 2019Source
  • OtherP51700005481 · D RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • OtherP51700013833 · G RERA.pdf · uploaded 20 Apr 2019Source
  • OtherP51700013833 · G RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • OtherP51700005481 · COMPLETION LETTER FENNEL D.pdf · uploaded 31 Dec 2019Source
  • Declaration Form BP51700013833 · FORM B (2) (2).pdf · uploaded 18 Feb 2025Source

Migrated

  • 1 PAN CardP51700003652 · pan card of Royale Urbanspace LLP 001.pdf · uploaded 21 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700003652 · COPY OF LAYOUT SECTOR 2.pdf · uploaded 21 Jul 2017Source
  • 1 PAN CardP51700013833 · pan card of Royale Urbanspace LLP 001.pdf · uploaded 21 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700013833 · LAYOUT PLAN.PDF · uploaded 21 Jul 2017Source
  • 1 Details of encumbrancesP51700003652 · INDEX 2 (FOR SECTOR 2).pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)P51700003652 · NA SEC II.pdf · uploaded 29 Jul 2017Source
  • 1 Details of encumbrancesP51700013833 · INDEX 2 (FOR SECTOR 2).pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)P51700013833 · SEC II.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of the legal title reportP51700003652 · Title Report.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BP51700003652 · Final New (H-Type).pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · H.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENGINEER'S CERTIFICATE (H-TYPE).pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)P51700003652 · CA CERTIFICATE.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterP51700003652 · Allotment Sec 2.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterP51700003652 · agreement.pdf · uploaded 31 Jul 2017Source
  • 1 PAN CardP51700005481 · LLP Pan Card.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of the legal title reportP51700005481 · Title Report.pdf · uploaded 31 Jul 2017Source
  • 1 Details of encumbrancesP51700005481 · INDEX 2 (FOR SECTOR 2).pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700005481 · Layout Plan (Sector II).PDF · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)P51700005481 · SEC II.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BP51700005481 · FENNEL 'D'.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700005481 · D.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700005481 · ENGINEER'S CERTIFICATE (D-TYPE).pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)P51700005481 · CA CERTIFICATE (D-TYPE).pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterP51700005481 · Allotment Sec 2.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterP51700005481 · Agreement.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of the legal title reportP51700013833 · TITLE REPORT.pdf · uploaded 1 Aug 2017Source
  • 1 Declaration in FORM BP51700013833 · Form - B (G Bldg) new.pdf · uploaded 23 Oct 2017Source
  • 1 Certificates of CA (Form 3)P51700013833 · CA CERTIFICATE (G-TYPE) new.pdf · uploaded 23 Oct 2017Source
  • 1 Proforma of Allotment letterP51700013833 · Royal City (G) final freeze.pdf · uploaded 23 Oct 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700003652 · SEC II.pdf · uploaded 4 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700005481 · SEC II.pdf · uploaded 4 Apr 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · Orchid A5 A6 Architects.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · Fennel H compressed.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of CA (Form 3)P51700003652 · FENNEL H FORM 3 MARCH 2018 NEW CORRECTED.pdf · uploaded 17 Apr 2019Source
  • 1 Certificates of CA (Form 5)P51700003652 · CA chanchal Bhandari Form 5 for Fennel H.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700005481 · FENNEL D ARCHITECTS.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700005481 · Fennel D compressed.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of CA (Form 3)P51700005481 · FENNEL D FORM 3 MARCH 2018.pdf · uploaded 17 Apr 2019Source
  • 1 Certificates of CA (Form 5)P51700005481 · CA chanchal Bhandari Form 5 for Fennel D.pdf · uploaded 17 Apr 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700013833 · Fennel G Architects.pdf · uploaded 17 Apr 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · Fennel G compressed.pdf · uploaded 17 Apr 2019Source
  • 2 Certificates of CA (Form 3)P51700013833 · FENNEL G FORM 3 MARCH 2018.pdf · uploaded 17 Apr 2019Source
  • 1 Certificates of CA (Form 5)P51700013833 · CA chanchal Bhandari Form 5 for Fennel G.pdf · uploaded 17 Apr 2019Source
  • 1 OtherP51700003652 · H RERA.pdf · uploaded 20 Apr 2019Source
  • 2 OtherP51700003652 · H RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • 1 OtherP51700005481 · D RERA.pdf · uploaded 20 Apr 2019Source
  • 2 OtherP51700005481 · D RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • 1 OtherP51700013833 · G RERA.pdf · uploaded 20 Apr 2019Source
  • 2 OtherP51700013833 · G RERA WEBSITE.pdf · uploaded 20 Apr 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700005481 · D1 D2 D3 D4 OC_compressed.pdf · uploaded 31 Dec 2019Source
  • 3 OtherP51700005481 · COMPLETION LETTER FENNEL D.pdf · uploaded 31 Dec 2019Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P51700005481 · Fennel D Form 4 Artichet Certificate.pdf · uploaded 27 Feb 2020Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700005481 · D1 D2 D3 D4 SOCIETY.pdf · uploaded 1 Oct 2022Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · ARCHITECTS CERTIFICATE H1-H2 2019.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · ARCHITECT CERFICATE H1- H2 (2020).pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · ARCHITECH CERTIF H1 - H2 (2020-2021).pdf · uploaded 26 Jun 2023Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700003652 · ARCHITECH CERTIF H1-H2 ( 2021-2022 ).pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENGINNER CERTIFICATE H-2019.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENGINEER CERTIFICATE H1-H1 (2020).pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENIGINEER CERTIF H1- H2 (2020- 2021).pdf · uploaded 26 Jun 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENGINEER CERTIF H1-H2 (21-12 2021 ).pdf · uploaded 26 Jun 2023Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700003652 · ENGINEER CERTIF H1-H2 (2022 ).pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of CA (Form 3)P51700003652 · CA FORM 3 H1H2 YR - 2018-2019.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of CA (Form 3)P51700003652 · FORM 3 H1H2 YR -2019-2020.pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of CA (Form 3)P51700003652 · CA FORM 3 H1H2 (2020-2021).pdf · uploaded 26 Jun 2023Source
  • 6 Certificates of CA (Form 3)P51700003652 · CA FOMR 3 H1-H2 ( 21-12-21).pdf · uploaded 26 Jun 2023Source
  • 7 Certificates of CA (Form 3)P51700003652 · CA FOMR 3 H1-H2( 31-03-22).pdf · uploaded 26 Jun 2023Source
  • 2 Certificates of CA (Form 5)P51700003652 · FORM 5 H1 - H2 2018-2019.pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of CA (Form 5)P51700003652 · FORM 5 H1-H2 (19-20).pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of CA (Form 5)P51700003652 · FORM 5 H1-H2 (20-21).pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of CA (Form 5)P51700003652 · FORM 5 H1-H2 (21-22).pdf · uploaded 26 Jun 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700013833 · ARCHITE CERTIFI BLD- G (18-19).pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700013833 · ARCHITE CERTIFI BLD- G (20-21).pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700013833 · ARCHITE CERTIFI BLD- G (21-2022).pdf · uploaded 26 Jun 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · ENGINEER CERTIF BLD-G (18-19)_compressed.pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · ENGINEER CERTIF BLD-G (19-20)_compressed.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · ENGINEER CERTIF BLD-G (20-21)_compressed.pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · ENGINEER CERTIF BLD-G (21-22)_compressed.pdf · uploaded 26 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P51700013833 · ARCHITE CERTIFI BLD- G (19-20).pdf · uploaded 26 Jun 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P51700013833 · ENGINEER CERTIF BLD-G (19-20)_compressed.pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of CA (Form 3)P51700013833 · FORM 3 G 2018-2019.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of CA (Form 3)P51700013833 · FROM 3 G (19-20).pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of CA (Form 3)P51700013833 · FROM 3 G (20-21).pdf · uploaded 26 Jun 2023Source
  • 6 Certificates of CA (Form 3)P51700013833 · FROM 3 G (22).pdf · uploaded 26 Jun 2023Source
  • 2 Certificates of CA (Form 5)P51700013833 · FROM 3 G (21).pdf · uploaded 26 Jun 2023Source
  • 3 Certificates of CA (Form 5)P51700013833 · FORM 5 G 2018-2019.pdf · uploaded 26 Jun 2023Source
  • 4 Certificates of CA (Form 5)P51700013833 · FORM 5 G (19-20).pdf · uploaded 26 Jun 2023Source
  • 5 Certificates of CA (Form 5)P51700013833 · FORM 5 G (20-21).pdf · uploaded 26 Jun 2023Source
  • 6 Certificates of CA (Form 5)P51700013833 · FORM 5 G (21-22).pdf · uploaded 26 Jun 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P51700013833 · FORM 5 G 2018-2019.pdf · uploaded 26 Jun 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P51700013833 · FORM 5 G (19-20).pdf · uploaded 26 Jun 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700003652 · Occupancy Certificate.pdf · uploaded 2 Jan 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700013833 · form 1.pdf · uploaded 17 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700013833 · form 2.pdf · uploaded 17 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700013833 · NA ORDER.pdf · uploaded 17 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700013833 · Sold inventory for rera wing G.pdf · uploaded 18 Jan 2025Source
  • 1 Certificates of CA (Form 3)P51700013833 · CA Certificate Form 3 Wing G(2024) (2).pdf · uploaded 14 Feb 2025Source
  • 1 Declaration about Commencement CertificateP51700013833 · Declartion of CC.pdf · uploaded 14 Feb 2025Source
  • 1 CERSAI detailsP51700013833 · Cersai declaration.pdf · uploaded 14 Feb 2025Source
  • 1 Declaration in FORM BP51700013833 · FORM B (2) (2).pdf · uploaded 18 Feb 2025Source
  • 1 Certificates of CA (Form 3)P51700013833 · CA Form 3.pdf · uploaded 28 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700013833 · Sold inventory for rera wing G (1).pdf · uploaded 28 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700013833 · form 5 20-21.pdf · uploaded 3 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P51700013833 · Form 2A(20-21).pdf · uploaded 3 Mar 2025Source
  • 2 Disclosure of sold/ booked inventoryP51700013833 · Sold inventory for rera wing G (1) (1).pdf · uploaded 3 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700013833 · form 5 21-22.pdf · uploaded 3 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P51700013833 · Form 2A(20-21).pdf · uploaded 3 Mar 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P51700013833 · Form2A(21-22).pdf · uploaded 3 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700013833 · Form2A( 22-23).pdf · uploaded 3 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700013833 · Form 5 (22-23).pdf · uploaded 3 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700013833 · Form2A(23-24).pdf · uploaded 3 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700013833 · Form 5 (23-24).pdf · uploaded 3 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)P51700013833 · LAYOUT AND G BUILDING PLAN_compressed (1).pdf · uploaded 5 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700013833 · CC.pdf · uploaded 5 Mar 2025Source
  • Form 1P51700013833 · Form 1_June 2025.pdf · uploaded 20 Dec 2025Source
  • Form 2P51700013833 · Form 2_June 2025.pdf · uploaded 20 Dec 2025Source
  • Form 3P51700013833 · Form 3_June 2025.pdf · uploaded 20 Dec 2025Source
  • Disclosure of Sold and Booked InventoryP51700013833 · Circular 29.pdf · uploaded 20 Dec 2025Source
  • Form 1P51700013833 · Form 1_Sep 25.pdf · uploaded 20 Dec 2025Source
  • Form 2P51700013833 · Form 2_Sep 25.pdf · uploaded 20 Dec 2025Source
  • Form 3P51700013833 · Form 3_Sep 25.pdf · uploaded 20 Dec 2025Source
  • Disclosure of Sold and Booked InventoryP51700013833 · Circular 29.pdf · uploaded 20 Dec 2025Source
  • Withdrawal Update Form 1P51700013833 · FOMR1 Q3 FENNEL G- 2025.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 1P51700013833 · FORM 1 Q4 March 2026.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 1P51700013833 · FORM 1 Q4 March 2026.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2P51700013833 · FORM 2 Q3 FENNEL G-2025.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2P51700013833 · FORM 2 Q4 March 2026.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2P51700013833 · FORM 2 Q4 March 2026.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3P51700013833 · FORM -3 Q3 FENNEL G-2025.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3P51700013833 · FORM -3 Q4 MARCH 2026.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3P51700013833 · FORM -3 Q4 MARCH 2026.pdf · uploaded 23 Jun 2026Source

Technical

  • DocumentP51700003652 · COPY OF LAYOUT SECTOR 2.pdf · uploaded 21 Jul 2017Source
  • DocumentP51700013833 · LAYOUT PLAN.PDF · uploaded 21 Jul 2017Source
  • DocumentP51700003652 · NA SEC II.pdf · uploaded 29 Jul 2017Source
  • DocumentP51700013833 · SEC II.pdf · uploaded 29 Jul 2017Source
  • DocumentP51700005481 · Layout Plan (Sector II).PDF · uploaded 31 Jul 2017Source
  • DocumentP51700005481 · SEC II.pdf · uploaded 31 Jul 2017Source
  • DocumentP51700013833 · LAYOUT AND G BUILDING PLAN_compressed (1).pdf · uploaded 5 Mar 2025Source

Technical (Architect)

  • DocumentP51700005481 · FENNEL D ARCHITECTS.pdf · uploaded 17 Apr 2019Source
  • DocumentP51700003652 · ARCHITECH CERTIF H1-H2 ( 2021-2022 ).pdf · uploaded 26 Jun 2023Source
  • DocumentP51700013833 · form 1.pdf · uploaded 17 Jan 2025Source
  • DocumentP51700013833 · FORM 1 Q4 March 2026.pdf · uploaded 23 Jun 2026Source

Technical (Engineer)

  • DocumentP51700005481 · Fennel D compressed.pdf · uploaded 17 Apr 2019Source
  • DocumentP51700003652 · ENGINEER CERTIF H1-H2 (2022 ).pdf · uploaded 26 Jun 2023Source
  • DocumentP51700013833 · form 2.pdf · uploaded 17 Jan 2025Source
  • DocumentP51700013833 · FORM 2 Q4 March 2026.pdf · uploaded 23 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals183

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
3
Unit types
1BHK, 1RK, 1 BHK, 1 RK, 2BHK, 1 BHK TYPE 1, 1 BHK TYPE 2, 1 RK TYPE 1, 1 RK TYPE 2276 units in all
Address
183, Shahapur, ShahapurPIN 421601
Village
Kalambhe, Shahapur taluka
Designated bank account
154
Developed in phases
Yes
Also registered as
Fennel G, Fennel H, Fennel D

Survey, CTS, gat or plot numbers

183

Boundaries

North
185
South
182
East
184
West
181

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking276 units

213 of 276 units booked (77%), as the promoter reported to MahaRERA

1BHK · 144 units1RK · 12 units1 BHK · 57 units1 RK · 2 units2BHK · 1 unit1 BHK TYPE 1 · 18 units1 BHK TYPE 2 · 10 units1 RK TYPE 1 · 30 units1 RK TYPE 2 · 2 units
RERABuildingTypeCarpet areaUnitsBooked
P51700005481Fennel D11BHK33.6 sq m · 362 sq ft1915
P51700005481Fennel D11RK23.84 sq m · 257 sq ft10
P51700005481Fennel D21 BHK33.6 sq m · 362 sq ft1912
P51700005481Fennel D21 RK23.84 sq m · 257 sq ft10
P51700005481Fennel D31 BHK33.6 sq m · 362 sq ft1913
P51700005481Fennel D31RK23.84 sq m · 257 sq ft10
P51700005481Fennel D41 BHK33.6 sq m · 362 sq ft1913
P51700005481Fennel D41 RK23.84 sq m · 257 sq ft10
Show all 34 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P51700013833Fennel G1BHK20.24 sq m · 218 sq ft76
P51700013833Fennel G1BHK21.42 sq m · 231 sq ft2113
P51700013833Fennel G1BHK21.59 sq m · 232 sq ft75
P51700013833Fennel G1BHK21.88 sq m · 236 sq ft75
P51700013833Fennel G1BHK22.05 sq m · 237 sq ft77
P51700013833Fennel G1BHK25.65 sq m · 276 sq ft77
P51700013833Fennel G1BHK25.76 sq m · 277 sq ft11
P51700013833Fennel G1BHK29.47 sq m · 317 sq ft77
P51700013833Fennel G1BHK30.73 sq m · 331 sq ft4140
P51700013833Fennel G1BHK30.87 sq m · 332 sq ft66
P51700013833Fennel G1BHK31.07 sq m · 334 sq ft1414
P51700013833Fennel G1RK17.41 sq m · 187 sq ft33
P51700013833Fennel G1RK17.44 sq m · 188 sq ft22
P51700013833Fennel G1RK17.45 sq m · 188 sq ft11
P51700013833Fennel G1RK17.48 sq m · 188 sq ft11
P51700013833Fennel G1RK18.69 sq m · 201 sq ft20
P51700013833Fennel G1RK25.19 sq m · 271 sq ft11
P51700013833Fennel G2BHK55.06 sq m · 593 sq ft11
P51700003652Fennel H 11 BHK TYPE 125.7 sq m · 277 sq ft97
P51700003652Fennel H 11 BHK TYPE 225.65 sq m · 276 sq ft54
P51700003652Fennel H 11 RK TYPE 117.41 sq m · 187 sq ft1510
P51700003652Fennel H 11 RK TYPE 218.74 sq m · 202 sq ft11
P51700003652Fennel H21 BHK TYPE 125.7 sq m · 277 sq ft95
P51700003652Fennel H21 BHK TYPE 225.65 sq m · 276 sq ft52
P51700003652Fennel H21 RK TYPE 117.41 sq m · 187 sq ft1511
P51700003652Fennel H21 RK TYPE 218.74 sq m · 202 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals12

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectTriarch Design Studio—P51700003652
ArchitectTriarch Design Studio—P51700013833
ArchitectTriarch Design Studio—P51700005481
EngineerVinayak Chopdekar—P51700003652
EngineerVinayak Chopdekar And Associates—P51700013833
EngineerVinayak Chopdekar & Associates—P51700005481
Registered real estate agentAshok Kumar Ramrang Dube—P51700005481
Registered real estate agentAshok Kumar Ramrang Dube—P51700003652
Show all 12 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Registered real estate agentAshok Kumar Ramrang Dube—P51700013833
Registered real estate agentJmb Enterprises—P51700013833
Registered real estate agentJmb Enterprises—P51700005481
Registered real estate agentJmb Enterprises—P51700003652

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology