Skip to content
Extended 4 mo4 floorsRERA P51700031172

Wing B, Mohan Tribeca

Deedo IDDP-THN-38QT-B

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked0%0 of 8 · MahaRERA
Completion30 Apr 202731 Dec 2026 · revised
Units & parking in Wing B
TypeCarpet areaUnitsBooked
Office space86.4 m² (930 sq.ft)20
Office space109.4 m² (1,177 sq.ft)20
Shop35.4 m² (381 sq.ft)40
As registered with MahaRERA
RERA registration
P51700031172 · registered 11 Oct 2021
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
4
Sanctioned floors (incl. basement, stilt, podium)
4
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
Deedo IDDP-THN-38QT-B
Questions about Wing B

When is Wing B due for completion?

The MahaRERA registration promises 31 Dec 2026, revised to 30 Apr 2027.

How many floors does Wing B have?

4 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology