Dream Avenue
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 82% of its units are booked.
Gandhare, Thane 421301 · Promoter: Dream Maruti Realtors
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 8 Jul 2021, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700029843
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700029843 | 8 Jul 2021 | 31 Dec 2025 | 31 Dec 2025 | Dream Maruti Realtors | Project page |
Documents106
1 document held by Deedo, 105 filings listed on MahaRERA's project page
Finance
- PAN CardCompany Pan.pdf · uploaded 26 Jun 2021Source
Legal
Migrated
- 1 PAN CardCompany Pan.pdf · uploaded 26 Jun 2021Source
- 1 Copy of the legal title reportSearch n Title report (1).pdf · uploaded 26 Jun 2021Source
- 1 Details of encumbrancesEncum cert.pdf · uploaded 26 Jun 2021Source
- 1 Copy of Layout Approval (in case of layout)Plan (1).pdf · uploaded 26 Jun 2021Source
Show all 106 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentPlan (1).pdf · uploaded 26 Jun 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCC (1).pdf · uploaded 26 Jun 2021Source
- 1 Declaration in FORM BForm B - Dream Maruti realtors 1.pdf · uploaded 26 Jun 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate (1).pdf · uploaded 26 Jun 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate (1).pdf · uploaded 26 Jun 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE (1).pdf · uploaded 26 Jun 2021Source
- 1 Proforma of Allotment letterA 1 (1).pdf · uploaded 26 Jun 2021Source
- 2 Proforma of Allotment letterA 2 (1).pdf · uploaded 26 Jun 2021Source
- 3 Proforma of Allotment letterA 3 (1).pdf · uploaded 26 Jun 2021Source
- 4 Proforma of Allotment letterA 4 (1).pdf · uploaded 26 Jun 2021Source
- 1 Declaration about Commencement CertificateDeclaratiom about CC.pdf · uploaded 28 Jun 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECTS CERTIFICATE.pdf · uploaded 25 Jul 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE.pdf · uploaded 25 Jul 2023Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY.pdf · uploaded 25 Jul 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Dream Avenue.pdf · uploaded 6 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2- Dream Avenue_compressed.pdf · uploaded 6 Nov 2023Source
- 2 Disclosure of sold/ booked inventorySOLD INVENTORY- Dream Avenue.pdf · uploaded 6 Nov 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Self declaration june 2023 dream avenue.pdf · uploaded 23 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)self declaration sept of dream avenue.pdf · uploaded 23 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-FY 21-22 DREAM AVENUE.pdf · uploaded 8 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5-FY 22-23 DREAM AVENUE.pdf · uploaded 8 Apr 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01_Dream Avenue_FY_24-25_Q1_Signed.pdf · uploaded 21 Mar 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01_Dream Avenue_FY_24-25_Q2_Signed.pdf · uploaded 21 Mar 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01_Dream Avenue_FY_24-25_Q3_Signed.pdf · uploaded 21 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03_Dream Avenue_FY_24-25_Q1_Signed.pdf · uploaded 21 Mar 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03_Dream Avenue_FY_24-25_Q2_Signed.pdf · uploaded 21 Mar 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03_Dream Avenue_FY_24-25_Q3_Signed.pdf · uploaded 21 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02_Dream Avenue_FY_24-25_Q1_Signed.pdf · uploaded 21 Mar 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02_Dream Avenue_FY_24-25_Q2_Signed.pdf · uploaded 21 Mar 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02_Dream Avenue_FY_24-25_Q3_Signed.pdf · uploaded 21 Mar 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 30-06-2023 AVENUE20250409_13422684.pdf · uploaded 18 Apr 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 30-09-2021 AVENUE20250409_13352371.pdf · uploaded 18 Apr 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 30-09-2022 AVENUE20250409_13394402.pdf · uploaded 18 Apr 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 30-09-2023 AVENUE20250409_13431609.pdf · uploaded 18 Apr 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 31-03-2022 AVENUE20250409_13373922.pdf · uploaded 18 Apr 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 31-03-2023 AVENUE20250409_13413808.pdf · uploaded 18 Apr 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 31-12-2021 AVENUE20250409_13364159.pdf · uploaded 18 Apr 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 31-12-2022 AVENUE20250409_13404386.pdf · uploaded 18 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE 30-06-2022 AVENUE20250409_13382351.pdf · uploaded 18 Apr 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30062023.pdf · uploaded 18 Apr 2025Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31122023.pdf · uploaded 18 Apr 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30092023.pdf · uploaded 18 Apr 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31032023.pdf · uploaded 18 Apr 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31122022.pdf · uploaded 18 Apr 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 30062022.pdf · uploaded 18 Apr 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31032022.pdf · uploaded 18 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31122021.pdf · uploaded 18 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30092021.pdf · uploaded 18 Apr 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30092022.pdf · uploaded 18 Apr 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-09-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-12-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-12-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-12-21 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-03-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-03-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-09-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-09-21 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-06-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-06-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)31-03-22 ANNEXURE C FORM-2A AVENUE.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)31-03-23 ANNEXURE C FORM-2A AVENUE.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)31-03-24 ANNEXURE C FORM-2A AVENUE.pdf · uploaded 18 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03_Dream Avenue.pdf · uploaded 28 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 architect certificate dream avenue.pdf · uploaded 5 May 2025Source
- Occupational CertificateFULL OC CERTIFICATE AVENUE.pdf · uploaded 12 Jul 2025Source
- Occupational CertificateAVENUE_COMPLETION LETTER.pdf · uploaded 12 Feb 2026Source
- Occupational CertificateForm 4 avenue.pdf · uploaded 12 Feb 2026Source
- Occupational CertificateGmail.pdf · uploaded 24 Apr 2026Source
Technical
Technical (Architect)
- DocumentForm 1- Dream Avenue.pdf · uploaded 6 Nov 2023Source
- DocumentForm 01_Dream Avenue_FY_24-25_Q1_Signed.pdf · uploaded 21 Mar 2025Source
- DocumentForm 01_Dream Avenue_FY_24-25_Q2_Signed.pdf · uploaded 21 Mar 2025Source
- DocumentForm 01_Dream Avenue_FY_24-25_Q3_Signed.pdf · uploaded 21 Mar 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 30-06-2022 AVENUE20250409_13382351.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 30-06-2023 AVENUE20250409_13422684.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 30-09-2021 AVENUE20250409_13352371.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 30-09-2022 AVENUE20250409_13394402.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 30-09-2023 AVENUE20250409_13431609.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 31-03-2022 AVENUE20250409_13373922.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 31-03-2023 AVENUE20250409_13413808.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 31-12-2021 AVENUE20250409_13364159.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 ARCH CERTIFICATE 31-12-2022 AVENUE20250409_13404386.pdf · uploaded 18 Apr 2025Source
- DocumentForm 1 architect certificate dream avenue.pdf · uploaded 5 May 2025Source
Technical (Engineer)
- DocumentFORM 2- Dream Avenue_compressed.pdf · uploaded 6 Nov 2023Source
- DocumentForm 02_Dream Avenue_FY_24-25_Q1_Signed.pdf · uploaded 21 Mar 2025Source
- DocumentForm 02_Dream Avenue_FY_24-25_Q2_Signed.pdf · uploaded 21 Mar 2025Source
- DocumentForm 02_Dream Avenue_FY_24-25_Q3_Signed.pdf · uploaded 21 Mar 2025Source
- Document30-06-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document30-06-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document30-09-21 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document30-09-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document30-09-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document31-03-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document31-03-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document31-12-21 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document31-12-22 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
- Document31-12-23 Form 2 ENG Certificate Avenue.pdf · uploaded 18 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsH NO 3, H NO 4 S NO 16
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK, Office space, Shop33 units in all
- Address
- S No 15, H No 4 - S No 16, H No 3, Gandhare, Kalyan WestPIN 421301
- Village
- Gandhare, Kalyan taluka
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 15-4-1
- South
- 16-2 And 16-8
- East
- 24 M Wide Road
- West
- 16-3
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking33 units
27 of 33 units booked (82%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 108.74 sq m · 1,170 sq ft | 22 | 20 |
| Office space | 24.56 sq m · 264 sq ft | 1 | 1 |
| Office space | 27.6 sq m · 297 sq ft | 1 | 1 |
| Office space | 30.34 sq m · 327 sq ft | 1 | 1 |
| Office space | 32.73 sq m · 352 sq ft | 1 | 1 |
| Office space | 39.16 sq m · 422 sq ft | 1 | 1 |
| Office space | 48.64 sq m · 524 sq ft | 1 | 1 |
| Office space | 53.58 sq m · 577 sq ft | 1 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 39.67 sq m · 427 sq ft | 1 | 0 |
| Shop | 40.04 sq m · 431 sq ft | 1 | 1 |
| Shop | 50.39 sq m · 542 sq ft | 1 | 0 |
| Shop | 59.06 sq m · 636 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Emerge Architects & Associates | — |
| Chartered accountant | D P Shejwal And Associates | — |
| Engineer | Pentacon Structural Consultants Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.