Its promised completion date, Sep 2020, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 36% of its units are booked.
Chikanghar, Thane 421301 · Promoter: Aarohi Development Corporation
Its promised completion date, Sep 2020, has passed and MahaRERA does not show it completed
- This projectRegistered 19 Aug 2017, completion promised 30 Sep 2020, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700008884
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700008884 | 19 Aug 2017 | 30 Sep 2020 | 30 Sep 2020 | Aarohi Development Corporation | Project page |
Documents24
1 document held by Deedo, 23 filings listed on MahaRERA's project page
Finance
- PAN CardAAROHI PAN CARD.pdf · uploaded 29 Jul 2017Source
Legal
Migrated
- 1 PAN CardAAROHI PAN CARD.pdf · uploaded 29 Jul 2017Source
- 1 Copy of the legal title reportTITLE.pdf · uploaded 29 Jul 2017Source
- 1 Details of encumbrancesencumbrance LETTER amikrupa_1.pdf · uploaded 29 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)AMI KRUPA LAYOUT.pdf · uploaded 29 Jul 2017Source
Show all 24 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)IOD COMMENCEMENT.pdf · uploaded 29 Jul 2017Source
- 1 Declaration in FORM Bform b declaration amikrupa.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 architect CERTIFICATE AMIKRUPA.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AMI KRUPA FORM 2 M R PATIL Engcertificate AMIKRUPA.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letteramikrupa draft undertaking.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)FINAL AMIKRUPA FORM 3 CA CERTIFICATE.pdf · uploaded 30 Jul 2017Source
- 2 Certificates of CA (Form 3)FINAL AMIKRUPA FORM 3 CA CERTIFICATE AREA CALCULATION.pdf · uploaded 30 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect AREA CERTIFICATE AMIKRUPA.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Apr 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)amikrupa form 1 architect progress certificate.pdf · uploaded 24 Apr 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAMIKRUPA CC.pdf · uploaded 11 Feb 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Architect Amikrupa (1).pdf · uploaded 16 Jun 2021Source
Technical
Technical (Architect)
- Documentamikrupa form 1 architect progress certificate.pdf · uploaded 24 Apr 2018Source
Technical (Engineer)
- DocumentAMI KRUPA FORM 2 M R PATIL Engcertificate AMIKRUPA.pdf · uploaded 29 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals95/11/1A, 95/1A1/4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK28 units in all
- Address
- 99-A12, 99b, 951-11a, 951a-14, 96c-1aPIN 421301
- Village
- Chikanghar, Kalyan taluka
- Location
- 19.24677, 73.14234
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Aavkar Building
- South
- Space For Future Expansion And Tenented Chawl
- East
- Plot Boundry
- West
- Amizarna Building
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
10 of 28 units booked (36%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 44.11 sq m · 475 sq ft | 7 | 1 |
| 1BHK | 44.69 sq m · 481 sq ft | 2 | 1 |
| 2BHK | 53.31 sq m · 574 sq ft | 5 | 4 |
| 2BHK | 58.49 sq m · 630 sq ft | 14 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Messers C M Belekar | — |
| Architect | Vitan Consultants | — |
| Engineer | M R Patil Consulting Engineers Pvt Ltd | — |
| Other | Amit Enterprises | — |
Source: MahaRERA project page. Contact details are not shown.