Wing B4 Lambodar

Certificate Signed

Badlapur (M Cl), Thane 421503 |Promoter: M K Patil Developers

Residential / Group HousingRERAP51700018374
26 Oct 2018Registered with MahaRERA
30 Jun 2020Promised completion
29 Jun 2022Revised completionPushed back 2 years
1Building
11,270Units registered907 booked (8%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK11,270 units in all
Address
Gut No 8p, Behind Deepali Park, ManjarliPIN 421503
Designated bank account
148
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years

The latest completion date on record passed 4 years and 4 months ago.

Registered
26 Oct 2018
Promised
30 Jun 2020
Revised
29 Jun 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001837426 Oct 201830 Jun 202029 Jun 2022M K Patil DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Lambodar911270

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

907 of 11,270 units booked (8%), as the promoter reported to MahaRERA

1BHK · 11,270 units
TypeCarpet areaUnitsBooked
1BHK30.97 sq m · 333 sq ft4040
1BHK30.97 sq m · 333 sq ft6030
1BHK30.97 sq m · 333 sq ft6010
1BHK30.97 sq m · 333 sq ft5040
1BHK30.97 sq m · 333 sq ft5030
1BHK30.97 sq m · 333 sq ft4010
1BHK30.97 sq m · 333 sq ft5010
1BHK30.97 sq m · 333 sq ft304304
Show all 28 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK30.97 sq m · 333 sq ft1040
1BHK30.97 sq m · 333 sq ft2030
1BHK30.97 sq m · 333 sq ft1030
1BHK30.97 sq m · 333 sq ft1010
1BHK30.97 sq m · 333 sq ft7040
1BHK30.97 sq m · 333 sq ft7030
1BHK30.97 sq m · 333 sq ft2040
1BHK30.97 sq m · 333 sq ft3010
1BHK30.97 sq m · 333 sq ft201201
1BHK30.97 sq m · 333 sq ft4030
1BHK30.97 sq m · 333 sq ft3030
1BHK30.97 sq m · 333 sq ft7010
1BHK30.97 sq m · 333 sq ft6040
1BHK41.42 sq m · 446 sq ft2020
1BHK41.42 sq m · 446 sq ft3020
1BHK41.42 sq m · 446 sq ft5020
1BHK41.42 sq m · 446 sq ft7020
1BHK41.42 sq m · 446 sq ft1020
1BHK41.42 sq m · 446 sq ft6020
1BHK41.42 sq m · 446 sq ft402402

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 37 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Legal

  • Declaration Form BForm B.pdf · uploaded 23 Oct 2018Source
  • Legal Title reportTitle Report.pdf · uploaded 23 Oct 2018Source
  • Other – LegalOther - legal.pdf · uploaded 27 Mar 2023Source

Migrated

  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 23 Oct 2018Source
  • 1 Details of encumbrancesEncumbrances Certificate.pdf · uploaded 23 Oct 2018Source
  • 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 23 Oct 2018Source
Show all 39 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)Plan.pdf · uploaded 23 Oct 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Oct 2018Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 23 Oct 2018Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 23 Oct 2018Source
  • 1 Proforma of Allotment letterAgreement Rera Format.pdf · uploaded 23 Oct 2018Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 23 Oct 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 26 Feb 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate lambodar.pdf · uploaded 26 Feb 2019Source
  • 2 Certificates of CA (Form 3)lambodar CA Certificate.pdf · uploaded 26 Feb 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGG CERTIFICATE.pdf · uploaded 20 May 2019Source
  • 1 Certificates of CA (Form 5)Lambodar_compressed.pdf · uploaded 20 May 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)form1 B4.pdf · uploaded 31 Jul 2019Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 B4.pdf · uploaded 31 Jul 2019Source
  • 3 Certificates of CA (Form 3)Form 3 B4.pdf · uploaded 31 Jul 2019Source
  • 2 Certificates of CA (Form 5)B4 Form 5.pdf · uploaded 28 Sep 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate - Form 1 (B4).pdf · uploaded 7 Nov 2019Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate - B4.pdf · uploaded 7 Nov 2019Source
  • 4 Certificates of CA (Form 3)FORM 3 B-4.pdf · uploaded 7 Nov 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)B4-Form 1.pdf · uploaded 25 Feb 2020Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)B4-Form 2.pdf · uploaded 25 Feb 2020Source
  • 5 Certificates of CA (Form 3)Form B4.pdf · uploaded 25 Feb 2020Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 B-4.pdf · uploaded 2 Oct 2020Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 B-4.pdf · uploaded 2 Oct 2020Source
  • 6 Certificates of CA (Form 3)lambodar.pdf · uploaded 2 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5 B4.pdf · uploaded 30 Sep 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentB4 OC.pdf · uploaded 27 Mar 2023Source
  • 1 Other – LegalOther - legal.pdf · uploaded 27 Mar 2023Source

Technical

  • DocumentPlan.pdf · uploaded 23 Oct 2018Source
  • Documentlayout.pdf · uploaded 23 Oct 2018Source

Technical (Architect)

  • DocumentForm 1 B-4.pdf · uploaded 2 Oct 2020Source

Technical (Engineer)

  • DocumentForm 2 B-4.pdf · uploaded 2 Oct 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Badlapur (M Cl), Ambarnath taluka

Survey, CTS, gat or plot numbers

GUTNO 8 P

Boundaries

North
Gut No 9 And 10 Land
South
Gut No 12 Land
East
Gut No 11 Land
West
Gut No 13 Land

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSandhya Rajesh Khambyat—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology