Vastu Vatika
Certificate SignedBadlapur (M Cl), Thane 421503 |Promoter: Shreeji Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 4
- Unit types
- 1RK, 1BHK50 units in all
- Address
- Survey No 69 Hissa No 9, Survey No 69 Hissa No 9, ShirgaonPIN 421503
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
The latest completion date on record passed 3 months ago.
- Registered
- 23 May 2019
- Promised
- 28 Mar 2026
- Revised
- 28 Jul 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700020918 | 23 May 2019 | 28 Mar 2026 | 28 Jul 2026 | Shreeji Enterprises | Project page |
4 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
21 of 50 units booked (42%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | 1RK | — | 0 | 0 |
| B Wing | 1RK | — | 0 | 0 |
| C Wing | 1BHK | 27.94 sq m · 301 sq ft | 5 | 1 |
| C Wing | 1BHK | 29.33 sq m · 316 sq ft | 5 | 1 |
| C Wing | 1BHK | 29.44 sq m · 317 sq ft | 5 | 2 |
| C Wing | 1BHK | 29.65 sq m · 319 sq ft | 1 | 1 |
| C Wing | 1BHK | 30.48 sq m · 328 sq ft | 5 | 4 |
| C Wing | 1BHK | 33.06 sq m · 356 sq ft | 1 | 1 |
Show all 15 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| D Wing | 1BHK | 23.14 sq m · 249 sq ft | 5 | 0 |
| D Wing | 1BHK | 29.26 sq m · 315 sq ft | 5 | 3 |
| D Wing | 1BHK | 29.33 sq m · 316 sq ft | 5 | 2 |
| D Wing | 1BHK | 30.61 sq m · 329 sq ft | 10 | 4 |
| D Wing | 1BHK | 30.97 sq m · 333 sq ft | 1 | 1 |
| D Wing | 1BHK | 31 sq m · 334 sq ft | 1 | 1 |
| D Wing | 1BHK | 33.06 sq m · 356 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 113 filings listed on MahaRERA's project page
Legal
Show all 114 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentC C COPY 1.pdf · uploaded 4 May 2019Source
- 1 Declaration in FORM BHITESH B PATEL_compressed.pdf · uploaded 4 May 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 (A).pdf · uploaded 4 May 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1(B).pdf · uploaded 4 May 2019Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 CWING.pdf · uploaded 4 May 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DWING.pdf · uploaded 4 May 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 4 May 2019Source
- 1 Certificates of CA (Form 3)form -3.pdf · uploaded 4 May 2019Source
- 1 Proforma of Allotment letterALLOTMENT.pdf · uploaded 4 May 2019Source
- 2 Proforma of Allotment letterFLAT SALE AGREEMENT.pdf · uploaded 4 May 2019Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 14 May 2019Source
- 1 Building Plan Approval (IOD)BUILDING PLAN.pdf · uploaded 14 May 2019Source
- 2 Details of encumbrancesNO ENCUM FINANCE.pdf · uploaded 25 Nov 2023Source
- 3 Details of encumbrancesNO ENCUM TITLE.pdf · uploaded 25 Nov 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 25 Nov 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCENT CERTIFICATE.pdf · uploaded 25 Nov 2023Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 31-03-2020.pdf · uploaded 25 Nov 2023Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 31-03-2021.pdf · uploaded 25 Nov 2023Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 31-03-2022.pdf · uploaded 25 Nov 2023Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 31-03-2023.pdf · uploaded 25 Nov 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 31-03-2020.pdf · uploaded 25 Nov 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 31-03-2021.pdf · uploaded 25 Nov 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 31-03-2022.pdf · uploaded 25 Nov 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 31-03-2023.pdf · uploaded 25 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A 31-03-2023.pdf · uploaded 25 Nov 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 25 Nov 2023Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD C WING.pdf · uploaded 25 Nov 2023Source
- 2 Disclosure of sold/ booked inventorySOLD UNSOLD D WING.pdf · uploaded 25 Nov 2023Source
- 2 Certificates of CA (Form 3)FORM 3 31-03-2020.pdf · uploaded 25 Nov 2023Source
- 3 Certificates of CA (Form 3)FORM 3 31-03-2021.pdf · uploaded 25 Nov 2023Source
- 4 Certificates of CA (Form 3)FORM 3 31-03-2022.pdf · uploaded 25 Nov 2023Source
- 5 Certificates of CA (Form 3)FORM 3 31-03-2023.pdf · uploaded 25 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 31-03-2020.pdf · uploaded 25 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 31-03-2021.pdf · uploaded 25 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 31-03-2022.pdf · uploaded 25 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 31-03-2023.pdf · uploaded 25 Nov 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION SEPARATE BANK AC.pdf · uploaded 25 Nov 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION REPORT TO ALLOTMENT LETTER.pdf · uploaded 25 Nov 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT AGREEMENT.pdf · uploaded 25 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A 31-03-2020.pdf · uploaded 30 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 31-03-2021.pdf · uploaded 30 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 31-03-2022.pdf · uploaded 30 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM 5 17-18.pdf · uploaded 30 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 18-19.pdf · uploaded 30 Nov 2023Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 9 Jan 2024Source
- 2 Building Plan Approval (IOD)LAYOUT.pdf · uploaded 9 Jan 2024Source
- 3 Building Plan Approval (IOD)LAYOUT.pdf · uploaded 22 Jan 2024Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 June.pdf · uploaded 22 Jan 2024Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Spet.pdf · uploaded 22 Jan 2024Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Dec.pdf · uploaded 22 Jan 2024Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE JUNE 23.pdf · uploaded 22 Jan 2024Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE SEP 2023.pdf · uploaded 22 Jan 2024Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE DEC 23.pdf · uploaded 22 Jan 2024Source
- 6 Certificates of CA (Form 3)FORM 3 APR JUN 23.pdf · uploaded 22 Jan 2024Source
- 7 Certificates of CA (Form 3)FORM 3 JUL SEP 23.pdf · uploaded 22 Jan 2024Source
- 8 Certificates of CA (Form 3)FORM 3 OCT DEC 23.pdf · uploaded 22 Jan 2024Source
- 2 Declaration in FORM BFORM B.pdf · uploaded 9 Mar 2024Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 C WING.pdf · uploaded 9 Mar 2024Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 D WING.pdf · uploaded 9 Mar 2024Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 9 Mar 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 24 WING C.pdf · uploaded 25 Mar 2025Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 JUNE 24 WING D.pdf · uploaded 25 Mar 2025Source
- 1 Certificates of CA (Form 3)FORM 3 MAR 24.pdf · uploaded 25 Mar 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 JUNE 24.pdf · uploaded 25 Mar 2025Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 24 WING C.pdf · uploaded 26 Mar 2025Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 SEPT 24 WING D.pdf · uploaded 26 Mar 2025Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 24 WING C.pdf · uploaded 26 Mar 2025Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 DEC 24 WING D.pdf · uploaded 26 Mar 2025Source
- 2 Certificates of CA (Form 3)FORM 3 JUN 24.pdf · uploaded 26 Mar 2025Source
- 3 Certificates of CA (Form 3)FORM 3 SEPT 24.pdf · uploaded 26 Mar 2025Source
- 4 Certificates of CA (Form 3)FORM 3 DEC 24.pdf · uploaded 26 Mar 2025Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 SEPT 24.pdf · uploaded 26 Mar 2025Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 DEC 24.pdf · uploaded 26 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 24.pdf · uploaded 26 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 MAR-24.pdf · uploaded 26 Mar 2025Source
- Form 1FORM 1 MAR 25.pdf · uploaded 13 Jun 2025Source
- Form 2FORM 2 MAR 25.pdf · uploaded 13 Jun 2025Source
- Form 3FORM 3 MAR 25.pdf · uploaded 13 Jun 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD MAR 25.pdf · uploaded 13 Jun 2025Source
- Withdrawal Update Form 1FORM 1 JUNE 25.pdf · uploaded 5 Nov 2025Source
- Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 5 Nov 2025Source
- Withdrawal Update Form 3FORM 3 JUNE 25.pdf · uploaded 5 Nov 2025Source
- Withdrawal Update Form 1FORM 1 SEPT 25.pdf · uploaded 21 Nov 2025Source
- Withdrawal Update Form 2FORM 2 SEPT 25.pdf · uploaded 21 Nov 2025Source
- Withdrawal Update Form 3FORM 3 SEPT 25.pdf · uploaded 21 Nov 2025Source
- Form 5 (FY 2024-2025)FORM 5 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 3FORM 3 DEC 25.pdf · uploaded 12 Feb 2026Source
- Form 5 (FY 2024-2025)FORM 5 25.pdf · uploaded 18 Feb 2026Source
Technical
Technical (Architect)
- DocumentFORM 1 JUNE 24 WING C.pdf · uploaded 25 Mar 2025Source
- DocumentFORM 1 JUNE 24 WING D.pdf · uploaded 25 Mar 2025Source
- DocumentFORM 1 SEPT 24 WING C.pdf · uploaded 26 Mar 2025Source
- DocumentFORM 1 SEPT 24 WING D.pdf · uploaded 26 Mar 2025Source
- DocumentFORM 1 DEC 24 WING C.pdf · uploaded 26 Mar 2025Source
- DocumentFORM 1 DEC 24 WING D.pdf · uploaded 26 Mar 2025Source
- DocumentFORM 1 DEC 25.pdf · uploaded 12 Feb 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Badlapur (M Cl), Ambarnath taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No 69 Hissa No 1
- South
- Survey No 69 Hissa No 3
- East
- Survey No 69 Hissa No 1
- West
- Survey No 69 Hissa No 8
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Arc Designers | — |
Source: MahaRERA project page. Contact details are not shown.