Surashree
Certificate SignedBadlapur (M Cl), Thane 421503 |Promoter: Yash Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 1 BHK, 1 RK, 2 BHK, Shop, Office53 units in all
- Address
- S no 68 Hissa no 11 P no 2, BADLAPUR GAON ROAD, RAMESH WADIPIN 421503
- Designated bank account
- 203
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2022
The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 23 May 2018
- Promised
- 30 Dec 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700016592 | 23 May 2018 | 30 Dec 2022 | 30 Dec 2022 | Yash Developers | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Surashree Wing A | 7 | 26 |
| Surashree Wing B | 7 | 27 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
44 of 53 units booked (83%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Surashree Wing A | 1 BHK | 32.57 sq m · 351 sq ft | 4 | 4 |
| Surashree Wing A | 1 BHK | 34.55 sq m · 372 sq ft | 1 | 1 |
| Surashree Wing A | 1 RK | 22.01 sq m · 237 sq ft | 1 | 1 |
| Surashree Wing A | 1 RK | 25.05 sq m · 270 sq ft | 3 | 2 |
| Surashree Wing A | 2 BHK | 44.01 sq m · 474 sq ft | 4 | 4 |
| Surashree Wing A | Shop | 4.01 sq m · 43 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 8.83 sq m · 95 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 8.88 sq m · 96 sq ft | 1 | 1 |
Show all 26 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Surashree Wing A | Shop | 11 sq m · 118 sq ft | 1 | 0 |
| Surashree Wing A | Shop | 11.02 sq m · 119 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 11.06 sq m · 119 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 11.24 sq m · 121 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 11.9 sq m · 128 sq ft | 1 | 0 |
| Surashree Wing A | Shop | 12.84 sq m · 138 sq ft | 1 | 0 |
| Surashree Wing A | Shop | 13 sq m · 140 sq ft | 1 | 0 |
| Surashree Wing A | Shop | 15.94 sq m · 172 sq ft | 1 | 1 |
| Surashree Wing A | Shop | 28.11 sq m · 303 sq ft | 1 | 0 |
| Surashree Wing A | Shop | 31.77 sq m · 342 sq ft | 1 | 0 |
| Surashree Wing B | 1 BHK | 28.85 sq m · 311 sq ft | 5 | 5 |
| Surashree Wing B | 1 BHK | 29.3 sq m · 315 sq ft | 4 | 4 |
| Surashree Wing B | 1 BHK | 29.59 sq m · 319 sq ft | 4 | 4 |
| Surashree Wing B | 1 BHK | 30.57 sq m · 329 sq ft | 5 | 5 |
| Surashree Wing B | 1 BHK | 30.7 sq m · 330 sq ft | 3 | 3 |
| Surashree Wing B | 1 RK | 21.23 sq m · 229 sq ft | 1 | 1 |
| Surashree Wing B | 1 RK | 24 sq m · 258 sq ft | 4 | 2 |
| Surashree Wing B | Office | 12.5 sq m · 135 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 42 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card.pdf · uploaded 25 Apr 2018Source
Legal
Migrated
- 1 PAN CardPan Card.pdf · uploaded 25 Apr 2018Source
- 1 Copy of Layout Approval (in case of layout)Plan pass 2.PDF · uploaded 25 Apr 2018Source
- 1 Building Plan Approval (IOD)Plan pass 2.PDF · uploaded 25 Apr 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 25 Apr 2018Source
Show all 43 documentsShow fewer documents
Migrated
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 25 Apr 2018Source
- 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 9 May 2018Source
- 1 Details of encumbrancesNON ENCUMBRANCES CERTIFICATE.pdf · uploaded 9 May 2018Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 9 May 2018Source
- 1 Proforma of Allotment letterRera_Draft_Agreement.pdf · uploaded 9 May 2018Source
- 2 Proforma of Allotment letterPROVISIONAL__ALLOTMENT__LETTER_SURASHREE.pdf · uploaded 9 May 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINNERS CERTIFICATE.pdf · uploaded 14 May 2018Source
- 1 Certificates of CA (Form 3)C A CERT.pdf · uploaded 14 May 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cerficate - 28-12-18.pdf · uploaded 16 Jan 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate - 28-12-18.pdf · uploaded 16 Jan 2019Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 16 Jan 2019Source
- 3 Certificates of CA (Form 3)Form3.pdf · uploaded 16 Jan 2019Source
- 4 Certificates of CA (Form 3)Form3.pdf · uploaded 16 Jan 2019Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch cer MARCH19.pdf · uploaded 10 Oct 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch cerJUNE19_compressed.pdf · uploaded 10 Oct 2019Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg cert MARCH19.pdf · uploaded 10 Oct 2019Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg cert JUNE19.pdf · uploaded 10 Oct 2019Source
- 5 Certificates of CA (Form 3)ca cer MARCH19.pdf · uploaded 10 Oct 2019Source
- 6 Certificates of CA (Form 3)ca cer JUNE19_compressed.pdf · uploaded 10 Oct 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)YASH DEVELOPERS FORM NO 5.pdf · uploaded 11 Nov 2019Source
- 7 Certificates of CA (Form 3)Form 3 Mar 2020.pdf · uploaded 25 Aug 2021Source
- 8 Certificates of CA (Form 3)Form 3 Mar 2021.pdf · uploaded 25 Aug 2021Source
- 9 Certificates of CA (Form 3)Form 3 June 2021.pdf · uploaded 25 Aug 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Yash Dev Form 5 2019-20.pdf · uploaded 8 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Yash Dev Form 5 2020-21.pdf · uploaded 8 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Yash Dev Form 5 2021-22.pdf · uploaded 8 Apr 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSurashree Building OC.pdf · uploaded 8 Apr 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Yash Dev.pdf · uploaded 8 Apr 2023Source
- 10 Certificates of CA (Form 3)form 3 yash developers Sep 21_compressed.pdf · uploaded 27 May 2023Source
- 11 Certificates of CA (Form 3)form 3 yash developers Dec 21_compressed.pdf · uploaded 27 May 2023Source
- 12 Certificates of CA (Form 3)yash developers form 3 Mar 22_compressed.pdf · uploaded 27 May 2023Source
Technical
Technical (Architect)
- Documentarch cerJUNE19_compressed.pdf · uploaded 10 Oct 2019Source
Technical (Engineer)
- Documentengg cert JUNE19.pdf · uploaded 10 Oct 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Badlapur (M Cl), Ambarnath taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- S no 68 P
- South
- 18 MT Wide D P Road
- East
- S no 86
- West
- S no 70
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Arti V Jamgaonkar | — |
Source: MahaRERA project page. Contact details are not shown.