Sonal Paradise
Certificate SignedBadlapur (M Cl), Thane 421503 |Promoter: Shubh Group
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1 BHK Landowner, 1BHK Landowner, 1BHKLandowner, 2BHK, 2BHK Landowner, Shop127 units in all
- Address
- Gut No 84, Gut No 86/1/A, Gut No 84, Gut No 86/1/A, , Valivali, Taluka Ambernath, Badlapur (West)PIN 421503
- Designated bank account
- 76
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 7 Jul 2023
- Promised
- 31 Dec 2026
- Revised
- 30 Apr 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700051894 | 7 Jul 2023 | 31 Dec 2026 | 30 Apr 2027 | Shubh Group | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Sonal Paradise | 10 | 127 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
10 of 127 units booked (8%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 30.49 sq m · 328 sq ft | 4 | 0 |
| 1BHK | 32.18 sq m · 346 sq ft | 3 | 1 |
| 1BHK | 32.88 sq m · 354 sq ft | 6 | 0 |
| 1BHK | 33.89 sq m · 365 sq ft | 5 | 0 |
| 1BHK | 34.87 sq m · 375 sq ft | 7 | 0 |
| 1BHK | 35.8 sq m · 385 sq ft | 5 | 2 |
| 1BHK | 37.28 sq m · 401 sq ft | 9 | 1 |
| 1BHK | 38.13 sq m · 410 sq ft | 10 | 5 |
Show all 26 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK Landowner | 33.89 sq m · 365 sq ft | 5 | 0 |
| 1BHK Landowner | 30.49 sq m · 328 sq ft | 4 | 0 |
| 1BHK Landowner | 32.88 sq m · 354 sq ft | 3 | 0 |
| 1BHK Landowner | 34.87 sq m · 375 sq ft | 3 | 0 |
| 1BHK Landowner | 35.8 sq m · 385 sq ft | 5 | 0 |
| 1BHK Landowner | 37.28 sq m · 401 sq ft | 1 | 0 |
| 1BHK Landowner | 38.13 sq m · 410 sq ft | 5 | 0 |
| 1BHKLandowner | 32.18 sq m · 346 sq ft | 17 | 0 |
| 2BHK | 42.22 sq m · 454 sq ft | 8 | 0 |
| 2BHK | 45.69 sq m · 492 sq ft | 8 | 0 |
| 2BHK | 46.95 sq m · 505 sq ft | 4 | 1 |
| 2BHK Landowner | 42.22 sq m · 454 sq ft | 2 | 0 |
| 2BHK Landowner | 45.69 sq m · 492 sq ft | 2 | 0 |
| 2BHK Landowner | 46.95 sq m · 505 sq ft | 6 | 0 |
| Shop | 10.72 sq m · 115 sq ft | 1 | 0 |
| Shop | 11 sq m · 118 sq ft | 2 | 0 |
| Shop | 15.12 sq m · 163 sq ft | 1 | 0 |
| Shop | 22.27 sq m · 240 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 77 filings listed on MahaRERA's project page
Finance
- PAN Card1 pan card subh group.pdf · uploaded 16 Jun 2023Source
Legal
Migrated
- 1 PAN Card1 pan card subh group.pdf · uploaded 16 Jun 2023Source
- 1 Copy of the legal title reportLegal Title Report for Rera_11zon.pdf · uploaded 16 Jun 2023Source
- 1 a Details of encumbrances concerned to Financeself declaration regarding no encumbrance.pdf · uploaded 16 Jun 2023Source
- 1 b Details of encumbrances concerned to Legalself declaration regarding no encumbrance.pdf · uploaded 16 Jun 2023Source
Show all 78 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Plan Layout.pdf · uploaded 16 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentFloor Plan.pdf · uploaded 16 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_11zon.pdf · uploaded 16 Jun 2023Source
- 1 Declaration about Commencement CertificateForm D - Declaration about CC.pdf · uploaded 16 Jun 2023Source
- 1 CERSAI detailsCERSAI Declaration.pdf · uploaded 16 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsHiral Patel Annexure A.pdf · uploaded 16 Jun 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsJayesh Jain Annexure A.pdf · uploaded 16 Jun 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsVipul Shah Annexure A.pdf · uploaded 16 Jun 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsJanardan Dayare Annexure A.pdf · uploaded 16 Jun 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsBaliram Karale Annexure A.pdf · uploaded 16 Jun 2023Source
- 1 Proforma of Agreement for saleDraft AFS_11zon.pdf · uploaded 16 Jun 2023Source
- 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 16 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 16 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment Letter.pdf · uploaded 16 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation wrt AFS.pdf · uploaded 16 Jun 2023Source
- 1 Declaration in FORM BForm B Vipul Shah_11zon.pdf · uploaded 17 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_11zon.pdf · uploaded 23 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1 30092023_11zon.pdf · uploaded 21 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Form 1 31122023.pdf · uploaded 21 Nov 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form 1 31032024.pdf · uploaded 21 Nov 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Form 1 30062024.pdf · uploaded 21 Nov 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Form 1 30092024.pdf · uploaded 21 Nov 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 Form 3 30062024 - converted.pdf · uploaded 21 Nov 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 Form 3 30092024.pdf · uploaded 21 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Form 3 31032024 - converted.pdf · uploaded 21 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Form 3 31122023 - converted.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Form 3 30092023.pdf · uploaded 21 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Form 2 30092023.pdf · uploaded 21 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form 2 31122023.pdf · uploaded 21 Nov 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Form 2 31032024.pdf · uploaded 21 Nov 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Form 2 30062024.pdf · uploaded 21 Nov 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Form 2 30092024.pdf · uploaded 21 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)signed Form 5 Shubh Group.pdf · uploaded 29 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shubh Group Engineer Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Q4.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certifiacte Q4.pdf · uploaded 17 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 3CA Certificate_11zon.pdf · uploaded 20 Jul 2025Source
- Form 5 (FY 2024-2025)Form 5 Shubh group Signed.pdf · uploaded 26 Sep 2025Source
- Withdrawal Update Form 1form 1 shubh group.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2form 2 shubh group.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3CA Certificate_11zon.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Shubh Group Form 1.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 2Shubh Group Form 2.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 3Form 3 Shubh Group 31122025.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 1Shubh Group Form 1.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Shubh Group Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 Shubh Group 31122025.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 Shubh Grp Q1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 Shubh Grp Q1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 Shubh Group FY 26-27 Q1.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 Signed Shubh Group.pdf · uploaded 29 Sep 2026Source
Technical
Technical (Architect)
- Document1 Form 1 30092023_11zon.pdf · uploaded 21 Nov 2024Source
- Document2 Form 1 31122023.pdf · uploaded 21 Nov 2024Source
- Document3 Form 1 31032024.pdf · uploaded 21 Nov 2024Source
- Document4 Form 1 30062024.pdf · uploaded 21 Nov 2024Source
- Document5 Form 1 30092024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 1 Architect Certificate Q4.pdf · uploaded 17 Apr 2025Source
- DocumentForm 1 Shubh Grp Q1.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- Document1 Form 2 30092023.pdf · uploaded 21 Nov 2024Source
- Document2 Form 2 31122023.pdf · uploaded 21 Nov 2024Source
- Document3 Form 2 31032024.pdf · uploaded 21 Nov 2024Source
- Document4 Form 2 30062024.pdf · uploaded 21 Nov 2024Source
- Document5 Form 2 30092024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 Engineer Certifiacte Q4.pdf · uploaded 17 Apr 2025Source
- DocumentForm 2 Shubh Grp Q1.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Badlapur (M Cl), Ambarnath taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gut No 87 Hissa No 1
- South
- Gut No 80
- East
- Gut No 85 Hissa No 1
- West
- Gut No 83
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | RAJ Associates | — |
| Chartered accountant | Mukesh Gurnani | — |
| Engineer | Atul Kudtarkar and Associates Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.