Shrutika Complex - A · Shrutika Complex
Badlapur (M Cl) · RERA P51700009040
IDBLD_0118058 floorsPromised date passed
8Sanctioned habitable floorsregistration certificate
31 May 2018Promised completion
Floors
8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 8
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 27.4 m² (295 sq.ft) | 7 | not published |
| 1 BHK | 28.2 m² (304 sq.ft) | 7 | not published |
| 1 BHK | 28.5 m² (306 sq.ft) | 7 | not published |
| 1 BHK | 28.6 m² (308 sq.ft) | 7 | not published |
| 1 BHK | 29 m² (312 sq.ft) | 7 | not published |
| 1 BHK | 29.2 m² (315 sq.ft) | 7 | not published |
| SHOP | 7.1 m² (76 sq.ft) | 4 | not published |
| SHOP | 7.4 m² (79 sq.ft) | 2 | not published |
| SHOP | 8.6 m² (93 sq.ft) | 1 | not published |
| SHOP | 9 m² (97 sq.ft) | 1 | not published |
Show all 14 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| SHOP | 9.1 m² (98 sq.ft) | 2 | not published |
| SHOP | 10.3 m² (110 sq.ft) | 1 | not published |
| SHOP | 11.1 m² (119 sq.ft) | 1 | not published |
| SHOP | 13.3 m² (143 sq.ft) | 1 | not published |
| Total | 55 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
Show all 11 activitiesShow fewer activities
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology