Shrutika Complex - A · Shrutika Complex

Badlapur (M Cl) · RERA P51700009040

IDBLD_0118058 floorsPromised date passed
8Sanctioned habitable floorsregistration certificate
31 May 2018Promised completion

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700009040 · registered 19 Aug 2017
Promised completion
31 May 2018
Sanctioned habitable floors
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 BHK27.4 m² (295 sq.ft)7not published
1 BHK28.2 m² (304 sq.ft)7not published
1 BHK28.5 m² (306 sq.ft)7not published
1 BHK28.6 m² (308 sq.ft)7not published
1 BHK29 m² (312 sq.ft)7not published
1 BHK29.2 m² (315 sq.ft)7not published
SHOP7.1 m² (76 sq.ft)4not published
SHOP7.4 m² (79 sq.ft)2not published
SHOP8.6 m² (93 sq.ft)1not published
SHOP9 m² (97 sq.ft)1not published
Show all 14 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
SHOP9.1 m² (98 sq.ft)2not published
SHOP10.3 m² (110 sq.ft)1not published
SHOP11.1 m² (119 sq.ft)1not published
SHOP13.3 m² (143 sq.ft)1not published
Total55

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0000
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology