Wing B · Shreeji Landmark Phase II
Badlapur (M Cl) · RERA P51700052645
IDBLD_0874237 floorsExtended 4 mo
7Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
13 of 40Units bookedMahaRERA project page
Floors
7 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51700052645 · registered 15 Sep 2023
- Promised completion
- 31 Dec 2026
- Revised completion
- 30 Apr 2027
- Sanctioned habitable floors
- 7
- ProjectId
- 45,370
- ProjectName
- SHREEJI LANDMARK PHASE II
- TotalUnitCount
- 40
- ProjectBuildingId
- 1,72,139
- BuildingNameNumber
- WING B
- FsiWithSanctionSqmts
- 7
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 40
- ProjectRegistartionNo
- P51700052645
- ProjectBuildingWingsId
- 1,75,596
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- WING B
- NoOfBuildingWingFloorProposed
- 8
- NoOfBuildingWingFloorHabitable
- 7
- NoOfBuildingWingFloorSanctioned
- 8
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 30 m² (323 sq.ft) | 13 | 2 |
| 1BHK | 33.3 m² (359 sq.ft) | 7 | 4 |
| 2BHK | 42.9 m² (461 sq.ft) | 14 | 5 |
| 2BHK | 43.1 m² (464 sq.ft) | 6 | 2 |
| Total | 40 | 13 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology