Raj Silverstone
Completion date passedBadlapur (M Cl), Thane 421503 |Promoter: Skyspace Builtek
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 6 months
P51700029081The latest completion date on record passed 3 years and 4 months ago.
- Registered
- 26 Apr 2021
- Promised
- 31 Dec 2022
- Revised
- 30 Jun 2023
Completion pushed back 1 year
P51700047261The latest completion date on record passed 3 months ago.
- Registered
- 15 Oct 2022
- Promised
- 31 Jul 2025
- Revised
- 31 Jul 2026
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700029081 | 26 Apr 2021 | 31 Dec 2022 | 30 Jun 2023 | Skyspace Builtek | Project page |
| P51700047261 | 15 Oct 2022 | 31 Jul 2025 | 31 Jul 2026 | Skyspace Builtek | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.