Olive · Palm

Badlapur (M Cl) · RERA P51700004695

IDBLD_05464013 floorsExtended 15 mo
13Sanctioned habitable floorsregistration certificate
28 Aug 2022Revised completionpromised 28 May 2021
0 of 95Units bookedMahaRERA project page

Floors

13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700004695 · registered 9 Aug 2017
Promised completion
28 May 2021
Revised completion
28 Aug 2022
Sanctioned habitable floors
13
ProjectId
10,949
ProjectName
Palm
TotalUnitCount
0
ProjectBuildingId
8,363
BuildingNameNumber
Olive
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P51700004695
ProjectBuildingWingsId
8,363
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Olive
NoOfBuildingWingFloorProposed
13
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
13

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK29.4 m² (316 sq.ft)470
2BHK37.8 m² (407 sq.ft)480
Total950
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology