Certificate Signed

Badlapur (M Cl), Thane 421503 |Promoter: Nina Developers

Residential / Group HousingRERAP51700027463
11 Dec 2020Registered with MahaRERA
30 Jun 2025Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Address
Gut No 113, Valvali, Badlapur WestPIN 421503
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2025

The latest completion date on record passed 1 year and 4 months ago.

Registered
11 Dec 2020
Promised
30 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002746311 Dec 202030 Jun 202530 Jun 2025Nina DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Mahi39—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo, 34 filings listed on MahaRERA's project page

Registration certificate

Migrated

  • 1 Details of encumbrancesDECLARATION ENCUMBRANCE.pdf · uploaded 21 Nov 2020Source
  • 1 Copy of Layout Approval (in case of layout)GUT BOOK.pdf · uploaded 21 Nov 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentNA ORDER.pdf · uploaded 21 Nov 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentMUNICIPAL BANDHKAM PERMISSION.pdf · uploaded 21 Nov 2020Source
  • 1 Declaration in FORM BDECLARATION FORM B.pdf · uploaded 21 Nov 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A_.pdf · uploaded 21 Nov 2020Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 21 Nov 2020Source
Show all 35 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reporttitle Certificate.pdf · uploaded 1 Dec 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentCONVEYNANCE DEED.pdf · uploaded 9 Dec 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Nina.pdf · uploaded 14 Jan 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RCC Nina_compressed.pdf · uploaded 14 Jan 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Nina-compressed.pdf · uploaded 14 Jan 2022Source
  • 1 PAN CardAdobe Scan Feb 06, 2021.pdf · uploaded 17 Jul 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentAdobe Scan Jul 17, 2022.pdf · uploaded 17 Jul 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Adobe Scan Jul 17, 2022 (1).pdf · uploaded 17 Jul 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Adobe Scan Feb 11, 2023 (2).pdf · uploaded 11 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form 3 Nina Developers_11zon.pdf · uploaded 16 Mar 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Adobe Scan 5 Apr 2023 (1).pdf · uploaded 6 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Adobe Scan 4 Apr 2023 (4) (3).pdf · uploaded 6 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Adobe Scan 8 Apr 2023 (2).pdf · uploaded 8 Apr 2023Source
  • 1 Declaration about Commencement CertificateFOrm D.pdf · uploaded 13 Jun 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold unsold.pdf · uploaded 13 Jun 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 13 Jun 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Jun 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)DOC-20240110-WA0007_ (2).pdf · uploaded 18 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryAdobe Scan 18-Jan-2024 (1) (1).pdf · uploaded 18 Jan 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDOC-20240105-WA0006_.pdf · uploaded 18 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA Form 5 Nina.pdf · uploaded 2 Apr 2024Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)Adobe Scan 2 May 2024.pdf · uploaded 2 May 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)MAHI SOCIETY CERTIFICATE.pdf · uploaded 10 Jan 2025Source

Technical

  • DocumentGUT BOOK.pdf · uploaded 21 Nov 2020Source
  • DocumentNA ORDER.pdf · uploaded 21 Nov 2020Source

Technical (Architect)

  • DocumentDOC-20240110-WA0007_ (2).pdf · uploaded 18 Jan 2024Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 14 Jun 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Badlapur (M Cl), Ambarnath taluka

Survey, CTS, gat or plot numbers

GUT NO 113

Boundaries

North
Gut No 111 Land
South
Gut No 102 And 103
East
Gut No 112 Land
West
Gut No 114 And 115 Land

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—

Source: MahaRERA project page. Contact details are not shown.