It is due for completion in Dec 2028, with no extension on record; no MahaRERA orders on record; 41% of its units are booked.

Godoli (Ct), Satara 415001 · Promoter: Unity Buildcon Group

DeliveryDue Dec 2028No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales41% booked12 of 29 units · as the promoter reported to MahaRERA
Unity Crown project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

It is due for completion in Dec 2028, with no extension on record

  • This projectRegistered 14 Mar 2024, completion promised 31 Dec 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52700055304
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5270005530414 Mar 202431 Dec 202831 Dec 2028Unity Buildcon GroupProject page
Documents64

1 document held by Deedo, 63 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD Firm.pdf · uploaded 27 Dec 2023Source

Legal

  • Legal Title reportLEGAL Title Report.pdf · uploaded 27 Dec 2023Source
  • Declaration Form Bdeclaration form B pramoter .pdf · uploaded 29 Dec 2023Source
  • Other – LegalPARTNERSHIP DEED.pdf · uploaded 15 Jan 2024Source

Migrated

  • 1 PAN CardPAN CARD Firm.pdf · uploaded 27 Dec 2023Source
  • 1 Copy of the legal title reportLEGAL Title Report.pdf · uploaded 27 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)11zon_merged-PDF (1)_11zon.pdf · uploaded 27 Dec 2023Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted development11zon_merged-PDF_11zon.pdf · uploaded 27 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC ORDER.pdf · uploaded 27 Dec 2023Source
  • 1 Proforma of Agreement for saleATS.pdf · uploaded 27 Dec 2023Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 27 Dec 2023Source
  • 1 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCES COMPRESS.pdf · uploaded 29 Dec 2023Source
  • 2 a Details of encumbrances concerned to FinanceFINANCIAL ENCUMBRANCES COMPRESS.pdf · uploaded 29 Dec 2023Source
  • 1 b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCES COMPRESS.pdf · uploaded 29 Dec 2023Source
  • 2 b Details of encumbrances concerned to LegalFINANCIAL ENCUMBRANCES COMPRESS.pdf · uploaded 29 Dec 2023Source
  • 1 Declaration in FORM Bdeclaration form B pramoter .pdf · uploaded 29 Dec 2023Source
  • 1 CERSAI detailsCARSAI REPORT_compress.pdf · uploaded 29 Dec 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdeclaretion of partners.pdf · uploaded 29 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT OF ALLOTMENT LATTER.pdf · uploaded 29 Dec 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentVerification of CC.pdf · uploaded 15 Jan 2024Source
  • 1 Declaration about Commencement CertificateDeclaration Abount CC.pdf · uploaded 15 Jan 2024Source
  • 1 Deviation Report with respect to model copy of AgreementAggreement Deviation.pdf · uploaded 15 Jan 2024Source
  • 1 Other – LegalPARTNERSHIP DEED.pdf · uploaded 15 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account declaration.pdf · uploaded 16 Jan 2024Source
  • 1 Other – TechnicalVerification of CC.pdf · uploaded 24 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Crown.pdf · uploaded 1 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct certificate 2-4-2024.pdf · uploaded 22 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct certificate 4-7-2024.pdf · uploaded 22 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct certificate 4-7-2024.pdf · uploaded 22 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arct certificate 3-10-2024.pdf · uploaded 22 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct certificate 5-1-2025.pdf · uploaded 22 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate 31-3-2024.pdf · uploaded 22 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate 30-6-2024.pdf · uploaded 22 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)cA certificate 30-9-2024.pdf · uploaded 22 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate 31-12-2024.pdf · uploaded 22 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engg certificate 5-4-2024.pdf · uploaded 22 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)engg certificate 2-7-2024.pdf · uploaded 22 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)engg certificate 4-10-2024.pdf · uploaded 22 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg certificate 1-1-2025.pdf · uploaded 22 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)engg certificate assurance 23-8-2024.pdf · uploaded 22 Feb 2025Source
  • Form 1FORM 1.pdf · uploaded 24 Jul 2025Source
  • Form 2FORM 2.pdf · uploaded 24 Jul 2025Source
  • Form 3CA CERTIFICATE FORM 3.pdf · uploaded 24 Jul 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 24 Jul 2025Source
  • Withdrawal Update Form 1FORM 1.PDF · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 2FORM 2.PDF · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 3FORM 3.PDF · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 1Crown -Form-1.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2Crown - Form - 2 .pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3Crown- From -3 .pdf · uploaded 27 Nov 2025Source
  • Occupational CertificateOC AND MAIL.pdf · uploaded 27 Nov 2025Source

Technical

  • Document11zon_merged-PDF_11zon.pdf · uploaded 27 Dec 2023Source
  • Document11zon_merged-PDF (1)_11zon.pdf · uploaded 27 Dec 2023Source
  • Other – TechnicalVerification of CC.pdf · uploaded 24 Jan 2024Source

Technical (Architect)

  • Documentarct certificate 4-7-2024.pdf · uploaded 22 Feb 2025Source
  • Documentarct certificate 4-7-2024.pdf · uploaded 22 Feb 2025Source
  • DocumentArct certificate 3-10-2024.pdf · uploaded 22 Feb 2025Source
  • Documentarct certificate 5-1-2025.pdf · uploaded 22 Feb 2025Source
  • DocumentCrown -Form-1.pdf · uploaded 27 Nov 2025Source

Technical (Engineer)

  • Documentengg certificate 2-7-2024.pdf · uploaded 22 Feb 2025Source
  • Documentengg certificate 4-10-2024.pdf · uploaded 22 Feb 2025Source
  • DocumentEngg certificate 1-1-2025.pdf · uploaded 22 Feb 2025Source
  • DocumentCrown - Form - 2 .pdf · uploaded 27 Nov 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals1191BPlot No 6

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1 BHK LAND OWNER, 2BHK, 2 BHK LAND OWNER29 units in all
Address
119-1B-Plot No 6, Shahunagar, ShahunagarPIN 415001
Village
Godoli (CT), Satara taluka
Designated bank account
43
Developed in phases
No

Survey, CTS, gat or plot numbers

1191BPlot No 6

Boundaries

North
Survey No 119-1A
South
9 Meter Wide Road
East
Plot No 5
West
Survey no 131

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking29 units

12 of 29 units booked (41%), as the promoter reported to MahaRERA

1BHK · 8 units1 BHK LAND OWNER · 7 units2BHK · 12 units2 BHK LAND OWNER · 2 units
TypeCarpet areaUnitsBooked
1BHK34.19 sq m · 368 sq ft33
1BHK34.91 sq m · 376 sq ft53
1 BHK LAND OWNER34.19 sq m · 368 sq ft40
1 BHK LAND OWNER34.91 sq m · 376 sq ft30
2BHK52.74 sq m · 568 sq ft60
2BHK53.44 sq m · 575 sq ft66
2 BHK LAND OWNER52.74 sq m · 568 sq ft10
2 BHK LAND OWNER53.44 sq m · 575 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAbhishek A Raut Raut—
Chartered accountantS J Doshi & Company—
EngineerVaibhav S Nikam—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology