Usha Enclave

Certificate Signed

Sangli Miraj Kupwad (M Corp.), Sangli 416416 |Promoter: Kalash Developers

13 Mar 2023Registered with MahaRERA
30 Apr 2026Promised completion
1Building
20Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—20 units in all
Address
CTS No. 12194, Mangalmurti Colony, Mangalmurti Colony, SangliPIN 416416
Designated bank account
43
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 16.79482, 73.91764
Usha Enclave is at latitude 16.79482, longitude 73.91764.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Apr 2026

The latest completion date on record passed 6 months ago.

Registered
13 Mar 2023
Promised
30 Apr 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5310005007613 Mar 202330 Apr 202630 Apr 2026Kalash DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Usha Enclave720

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 units registered

— · 20 units
TypeCarpet areaUnits
——20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 98 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardKalash Pan Card.pdf · uploaded 15 Feb 2023Source

Legal

  • Legal Title reportKalash Search Report_Compressed.pdf · uploaded 20 Feb 2023Source
  • Declaration Form BForm B promoter.pdf · uploaded 20 Feb 2023Source

Migrated

  • 1 PAN CardKalash Pan Card.pdf · uploaded 15 Feb 2023Source
  • 1 Copy of the legal title reportKalash Search Report_Compressed.pdf · uploaded 20 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter Legal.pdf · uploaded 20 Feb 2023Source
Show all 100 documentsShow fewer documents

Migrated

  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter Finance.pdf · uploaded 20 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter Legal.pdf · uploaded 20 Feb 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter Finance.pdf · uploaded 20 Feb 2023Source
  • 1 Copy of Layout Approval (in case of layout)Kalash SMKC Plan -Compressed.pdf · uploaded 20 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentKalash SMKC Plan -Compressed.pdf · uploaded 20 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentKalash CC.pdf · uploaded 20 Feb 2023Source
  • 1 Declaration in FORM BForm B promoter.pdf · uploaded 20 Feb 2023Source
  • 1 CERSAI detailsKalash CERSAI_Search_Report_- New our end.pdf · uploaded 20 Feb 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Kalash CA Certificate signed_Compressed.pdf · uploaded 20 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A merged.pdf · uploaded 20 Feb 2023Source
  • 1 Proforma of Allotment letterNew Allotment Letter.pdf · uploaded 20 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration Format A.pdf · uploaded 20 Feb 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report of Allotment Signed.pdf · uploaded 20 Feb 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 25 Feb 2023Source
  • 1 Proforma of Agreement for saleAFS_Usha Enclave_Kalash Developers_02032023.pdf · uploaded 3 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNew Deviation Report Agreement for Sale_Compressed.pdf · uploaded 3 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL_Arch_Q4_22-23.pdf · uploaded 23 May 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL_Engg_Q4_22-23.pdf · uploaded 23 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL_Arch_Q4_22-23.pdf · uploaded 25 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL_Engg_Q4_22-23.pdf · uploaded 25 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)KL_CA_Q4_22-23_compressed.pdf · uploaded 25 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL Form 1 Jun 23.pdf · uploaded 19 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL Form 2 Jun 23.pdf · uploaded 19 Jul 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)KL Form 3 Jun 23_compressed (1).pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- Usha Enclave as on 2022-23.pdf · uploaded 6 Oct 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL Form 1 Sep 23.pdf · uploaded 13 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL Form 2 Sep 23.pdf · uploaded 13 Oct 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)KL Form 3 Sep 23_compressed.pdf · uploaded 13 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Usha Enclave.pdf · uploaded 26 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_KL_Dec23_11zon.pdf · uploaded 12 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_KL_Dec23_11zon.pdf · uploaded 16 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Kalash_Dec23.pdf · uploaded 19 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL_FORM 1_MAR 24.pdf · uploaded 21 Apr 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL_FORM 2_MAR 24.pdf · uploaded 21 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryKL_UNSOLD_MAR 24.pdf · uploaded 21 Apr 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)KL_FORM 3_MAR 24.pdf · uploaded 21 Apr 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)KL_FORM 1_JUNE 24.pdf · uploaded 20 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)KL_FORM 2_JUNE 24.pdf · uploaded 20 Jul 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectKL_UNSOLD INVENTORY_JUNE 24.pdf · uploaded 20 Jul 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)KL_FORM 3_JUNE 24.pdf · uploaded 20 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 KL Sep 24.pdf · uploaded 25 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 KL Sep24.pdf · uploaded 25 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryKL_UNSOLD INVENTORY_JUNE 24.pdf · uploaded 25 Oct 2024Source
  • 3 Disclosure of sold/ booked inventoryInventory_KL_Sep24.pdf · uploaded 25 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_KL_Sep 24.pdf · uploaded 28 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_Usha_Mar 2024.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 KL Dec 24.pdf · uploaded 25 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 KL Dec 24-compressed.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 KL Dec 24.pdf · uploaded 25 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory KL Dec 24.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_KL_Mar 25.pdf · uploaded 22 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2_KL_Mar 25.pdf · uploaded 22 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryInventory KL Mar 25.pdf · uploaded 22 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_KL_2023-24.pdf · uploaded 22 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_KL_Mar 25-compressed.pdf · uploaded 24 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)KALASH.PDF · uploaded 29 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentKalash Revised Building Permission.pdf · uploaded 29 Apr 2025Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 29 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - FY 2023-24.pdf · uploaded 29 Apr 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 1Form 1_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 2Form 2_Kalash_Sep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Withdrawal Update Form 3Form 3_KalashSep 25.pdf · uploaded 7 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5 - Usha Enclave for FY 2024-25.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Usha Dec 25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Usha Dec 25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3Form 3_KL_Dec 25.pdf · uploaded 23 Jan 2026Source

Technical

  • DocumentKalash SMKC Plan -Compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentKalash SMKC Plan -Compressed.pdf · uploaded 20 Feb 2023Source
  • DocumentKALASH.PDF · uploaded 29 Apr 2025Source

Technical (Architect)

  • DocumentForm 1 KL Sep 24.pdf · uploaded 25 Oct 2024Source
  • DocumentForm 1 KL Dec 24.pdf · uploaded 25 Jan 2025Source
  • DocumentForm 1_KL_Mar 25.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 1 Usha Dec 25.pdf · uploaded 23 Jan 2026Source

Technical (Engineer)

  • DocumentForm 2 KL Sep24.pdf · uploaded 25 Oct 2024Source
  • DocumentForm 2 KL Dec 24.pdf · uploaded 25 Jan 2025Source
  • DocumentForm2_KL_Mar 25.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 2 Usha Dec 25.pdf · uploaded 23 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sangli Miraj Kupwad (M Corp.), Miraj taluka

Survey, CTS, gat or plot numbers

CTS No. 12194

Boundaries

North
CTS No 12195
South
6 Mtr Road
East
9 Mtr Road
West
Survey Number 445-4

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrakash L Patil—
Chartered accountantNursal Banu Sayed—
Chartered accountantR K Kale & Associates—
EngineerMarkarand M Shinde—
EngineerPravin Pise—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology