Suyashh Metropole

Certificate Signed

Sangli Miraj Kupwad (M Corp.), Sangli 416416 |Promoter: Suyashh Subhash Patil

19 Aug 2022Registered with MahaRERA
31 Dec 2024Promised completion
30 Dec 2025Revised completionPushed back 1 year
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Address
Ext C S No 635, Behind Dcc Bank Hed Office Pushpraj Chowk Sangli, Pushpraj ChowkPIN 416416
Designated bank account
41
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 16.85292, 74.58152
Suyashh Metropole is at latitude 16.85292, longitude 74.58152.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 10 months ago.

Registered
19 Aug 2022
Promised
31 Dec 2024
Revised
30 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5310004659019 Aug 202231 Dec 202430 Dec 2025Suyashh Subhash PatilProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Suyashh Metropole8—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo, 105 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN OF SUYASHH PAATIL.pdf · uploaded 15 Jun 2022Source

Legal

  • Legal Title reportlegal title report.pdf · uploaded 15 Jun 2022Source
  • Declaration Form BFORM B (SUYASH PATIL ).pdf · uploaded 15 Jun 2022Source
  • Other – LegalDEVLOPMENT AGREEMENT.pdf · uploaded 25 Jul 2022Source
  • Declaration Form Bform - B.pdf · uploaded 9 Apr 2025Source

Migrated

  • 1 PAN CardPAN OF SUYASHH PAATIL.pdf · uploaded 15 Jun 2022Source
Show all 107 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportlegal title report.pdf · uploaded 15 Jun 2022Source
  • 1 Copy of Layout Approval (in case of layout)mojani nakasha.pdf · uploaded 15 Jun 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentDRAWING.pdf · uploaded 15 Jun 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentBANDHKAM PARWANA.pdf · uploaded 15 Jun 2022Source
  • 1 Declaration about Commencement Certificatedeclaration about commencement certificate.pdf · uploaded 15 Jun 2022Source
  • 1 Declaration in FORM BFORM B (SUYASH PATIL ).pdf · uploaded 15 Jun 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 15 Jun 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 engineers certificate.pdf · uploaded 15 Jun 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200239845317_For_Asset_Based_Search_16_06_2022_10_44_50_953.pdf · uploaded 16 Jun 2022Source
  • 1 Proforma of Allotment letterallotment letter as per rera 31.pdf · uploaded 14 Jul 2022Source
  • 1 Other – LegalDEVLOPMENT AGREEMENT.pdf · uploaded 25 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCE certificate FINANCIAL.pdf · uploaded 27 Jul 2022Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCE certificate LEGAL.pdf · uploaded 27 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)c a certificate.pdf · uploaded 27 Jul 2022Source
  • 2 Proforma of Allotment letteragreement to sale as per format rera.pdf · uploaded 27 Jul 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration separate account.pdf · uploaded 27 Jul 2022Source
  • 1 Deviation Report with respect to Allotment letterDEVETION allotment letter.pdf · uploaded 27 Jul 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDEVETION MODEL AGREEMENT.pdf · uploaded 27 Jul 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 30-9-22.pdf · uploaded 5 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 31-12-2022.pdf · uploaded 5 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CER - 31-3-23.pdf · uploaded 5 Mar 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 30-6-23.pdf · uploaded 5 Mar 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CER - 30-9-23.pdf · uploaded 5 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CER- 31-12-23.pdf · uploaded 5 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 10-10-2022.pdf · uploaded 5 Mar 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - 10-01-2023.pdf · uploaded 5 Mar 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - 10-4-2023.pdf · uploaded 5 Mar 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - 10-7-23.pdf · uploaded 5 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - 10-10-23.pdf · uploaded 5 Mar 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - 10-1-2024.pdf · uploaded 5 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)quality assurance certificate 12-4-2023.pdf · uploaded 5 Mar 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 30-9-22.pdf · uploaded 5 Mar 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 31-12-22.pdf · uploaded 5 Mar 2024Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 31-3-2023.pdf · uploaded 5 Mar 2024Source
  • 4 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 30-6-23.pdf · uploaded 5 Mar 2024Source
  • 5 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 30-9-23.pdf · uploaded 5 Mar 2024Source
  • 6 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 31-3-2023.pdf · uploaded 5 Mar 2024Source
  • 7 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - 31-12-23.pdf · uploaded 5 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE-30-09-2022.pdf · uploaded 5 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CRTIFICATE - 31-12-2022.pdf · uploaded 5 Mar 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CER - 31-03-2023.pdf · uploaded 5 Mar 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CER- 30-6-23.pdf · uploaded 5 Mar 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CER - 30-9-23.pdf · uploaded 5 Mar 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CER - 31-12-23.pdf · uploaded 5 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ANNUAL REPORT STATEMENT OF ACC.pdf · uploaded 5 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 310324.pdf · uploaded 10 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 31032024.pdf · uploaded 10 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 310324.pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD 310324.pdf · uploaded 10 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 23-24.pdf · uploaded 10 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 30-06-24.pdf · uploaded 11 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 30-09-24.pdf · uploaded 11 Mar 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 31-12-24.pdf · uploaded 11 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM - 3 300624.pdf · uploaded 11 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 30-09-24.pdf · uploaded 11 Mar 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31122024.pdf · uploaded 11 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD 30-06-24.pdf · uploaded 11 Mar 2025Source
  • 3 Disclosure of sold/ booked inventorySOLD UNSOLD 30-09-24.pdf · uploaded 11 Mar 2025Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD 31-12-24.pdf · uploaded 11 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30-09-22.pdf · uploaded 14 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-12-22.pdf · uploaded 14 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-03-23.pdf · uploaded 14 Mar 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30-06-23.pdf · uploaded 14 Mar 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30-09-23.pdf · uploaded 14 Mar 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-12-23.pdf · uploaded 14 Mar 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-03-24.pdf · uploaded 14 Mar 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30-06-24.pdf · uploaded 14 Mar 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 30-09-24.pdf · uploaded 14 Mar 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 31-12-24.pdf · uploaded 14 Mar 2025Source
  • 1 Declaration in FORM Bform - B.pdf · uploaded 9 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD-UNSOLD 31-12-24.pdf · uploaded 9 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form-1.pdf · uploaded 27 Jun 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3.pdf · uploaded 27 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form-2.pdf · uploaded 27 Jun 2025Source
  • 1 Disclosure of sold/ booked inventorysold-unsold.pdf · uploaded 27 Jun 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSER ANNEXURE-A.pdf · uploaded 27 Jun 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form-2A.pdf · uploaded 27 Jun 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectSICURED-UNSICURED.pdf · uploaded 27 Jun 2025Source

Technical

  • Documentmojani nakasha.pdf · uploaded 15 Jun 2022Source
  • DocumentDRAWING.pdf · uploaded 15 Jun 2022Source

Technical (Architect)

  • DocumentARCHITECT CER- 31-12-23.pdf · uploaded 5 Mar 2024Source
  • DocumentFORM -1 310324.pdf · uploaded 10 Mar 2025Source
  • DocumentFORM -1 30-06-24.pdf · uploaded 11 Mar 2025Source
  • DocumentFORM -1 30-09-24.pdf · uploaded 11 Mar 2025Source
  • DocumentFORM -1 31-12-24.pdf · uploaded 11 Mar 2025Source
  • Documentform-1.pdf · uploaded 27 Jun 2025Source

Technical (Engineer)

  • DocumentFORM 2 - 10-1-2024.pdf · uploaded 5 Mar 2024Source
  • DocumentFORM-2 310324.pdf · uploaded 10 Mar 2025Source
  • DocumentFORM-2 30-09-22.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 31-12-22.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 31-03-23.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 30-06-23.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 30-09-23.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 31-12-23.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 31-03-24.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 30-06-24.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 30-09-24.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM-2 31-12-24.pdf · uploaded 14 Mar 2025Source
  • Documentform-2.pdf · uploaded 27 Jun 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sangli Miraj Kupwad (M Corp.), Miraj taluka

Survey, CTS, gat or plot numbers

EXT C S NO 635

Boundaries

North
Municipal Road
South
Bol
East
Ext C T S No 634
West
Ext Cts No 636

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSachin Kanoje—
Chartered accountantmeghana mahesh jadhav—
EngineerAkshaykumar Anil Patil—
EngineerEr SAGAR suryakant shete—
Othera b kulkarni—

Source: MahaRERA project page. Contact details are not shown.