Ews B · Construction of 88 EWS, 32 LIG and 16 MIG tenaments under PMAY Scheme at S No 215/3, Sangli
Sangli Miraj Kupwad (M Corp.) · RERA P53100016715
IDBLD_0644324 floorsPromised date passed
4Sanctioned habitable floorsregistration certificate
30 Dec 2021Revised completionpromised 30 Dec 2021
0 of 24Units bookedMahaRERA project page
Floors
4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P53100016715 · registered 5 Jun 2018
- Promised completion
- 30 Dec 2021
- Revised completion
- 30 Dec 2021
- Sanctioned habitable floors
- 4
- ProjectId
- 11,034
- ProjectName
- Construction of 88 EWS, 32 LIG and 16 MIG tenaments under PMAY Scheme at S No 215/3, Sangli
- TotalUnitCount
- 0
- ProjectBuildingId
- 49,299
- BuildingNameNumber
- EWS B
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P53100016715
- ProjectBuildingWingsId
- 49,299
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- EWS B
- NoOfBuildingWingFloorProposed
- 4
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 4
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| One BHK L | 31.7 m² (342 sq.ft) | 8 | 0 |
| One BHK S | 31.4 m² (338 sq.ft) | 16 | 0 |
| Total | 24 | 0 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology