Skip to content

Bhirangi Landmark

Certificate Signed

Sangli Miraj Kupwad (M Corp.), Sangli 416415 |Promoter: Ashirwad Developers

22 Jan 2018Registered with MahaRERA
2 Jan 2022Promised completion
1Building
16Units registered3 booked (19%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
101, 102, 201, 202, 203, 301, 302, 303, 401, 402, 403, G01, G02, Ug01, Ug02, Ug0316 units in all
Address
8357a, Sangli Miraj Road, VishrambagPIN 416415
Designated bank account
119
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 16.84776, 74.59664
Bhirangi Landmark is at latitude 16.84776, longitude 74.59664.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 2 Jan 2022

The latest completion date on record passed 4 years and 9 months ago.

Registered
22 Jan 2018
Promised
2 Jan 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5310001502522 Jan 20182 Jan 20222 Jan 2022Ashirwad DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bhirangi Landmark616

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

3 of 16 units booked (19%), as the promoter reported to MahaRERA

101 · 1 unit102 · 1 unit201 · 1 unit202 · 1 unit203 · 1 unit301 · 1 unit302 · 1 unit303 · 1 unit401 · 1 unit402 · 1 unit403 · 1 unitG01 · 1 unitG02 · 1 unitUg01 · 1 unitUg02 · 1 unitUg03 · 1 unit
TypeCarpet areaUnitsBooked
10139.67 sq m · 427 sq ft11
10228.22 sq m · 304 sq ft11
20119.52 sq m · 210 sq ft11
20219.34 sq m · 208 sq ft10
20328.22 sq m · 304 sq ft10
30119.52 sq m · 210 sq ft10
30219.34 sq m · 208 sq ft10
30328.22 sq m · 304 sq ft10
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
40119.52 sq m · 210 sq ft10
40219.34 sq m · 208 sq ft10
40328.22 sq m · 304 sq ft10
G0115.13 sq m · 163 sq ft10
G0218.55 sq m · 200 sq ft10
Ug0125.05 sq m · 270 sq ft10
Ug0229.25 sq m · 315 sq ft10
Ug0324.46 sq m · 263 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 32 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardAshirwad Developers PAN Card.pdf · uploaded 10 Jan 2018Source

Legal

  • Legal Title reportTitle and Search report.pdf · uploaded 10 Jan 2018Source
  • Declaration Form BDeclaration Form B.pdf · uploaded 10 Jan 2018Source

Migrated

  • 1 PAN CardAshirwad Developers PAN Card.pdf · uploaded 10 Jan 2018Source
  • 1 Copy of the legal title reportTitle and Search report.pdf · uploaded 10 Jan 2018Source
  • 1 Details of encumbrancesNO ENCUMBRANCE CERTIFICATE.pdf · uploaded 10 Jan 2018Source
  • 1 Copy of Layout Approval (in case of layout)Sub Division Plan.pdf · uploaded 10 Jan 2018Source
Show all 33 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)Approved Plan.PDF · uploaded 10 Jan 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 10 Jan 2018Source
  • 1 Declaration in FORM BDeclaration Form B.pdf · uploaded 10 Jan 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 10 Jan 2018Source
  • 1 Proforma of Allotment letterPossession Receipt and Agreement To Sale.pdf · uploaded 10 Jan 2018Source
  • 2 Certificates of CA (Form 3)BLM CA Certificate 31-3-18.pdf · uploaded 21 Apr 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 BLM Architect Certificate July 18.pdf · uploaded 16 Jul 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 BLM Engineer Certificate July 18.pdf · uploaded 16 Jul 2018Source
  • 3 Certificates of CA (Form 3)Form 3 BLM CA Certificate July 18.pdf · uploaded 16 Jul 2018Source
  • 4 Certificates of CA (Form 3)BLM CA CERTIFICATE SEP 18.pdf · uploaded 19 Oct 2018Source
  • 1 Certificates of CA (Form 5)FORM-5 Audit Report 2017-18.pdf · uploaded 20 Dec 2018Source
  • 5 Certificates of CA (Form 3)Form 03 CA Certificate 09-01-2019.pdf · uploaded 18 Jan 2019Source
  • 6 Certificates of CA (Form 3)CA CERTIFICATE MARCH 19.pdf · uploaded 19 Apr 2019Source
  • 2 Certificates of CA (Form 5)FORM 5- AUDIT REPORT MARCH 19.pdf · uploaded 19 Apr 2019Source
  • 2 Building Plan Approval (IOD)BHIRANGI LANDMARK REVISED SANCTION.pdf · uploaded 29 Apr 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)BLM ENGINEER CERTIFICATE JUNE 19.pdf · uploaded 3 Aug 2019Source
  • 7 Certificates of CA (Form 3)BLM CA CERTIFICATE JUNE 19.pdf · uploaded 3 Aug 2019Source
  • 8 Certificates of CA (Form 3)Form 3 BLM CA Certificate Sept 19.pdf · uploaded 18 Nov 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentBhirangi Landmark Completion Certificate.pdf · uploaded 15 Jan 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4- Completion 14-01-2020.pdf · uploaded 15 Jan 2020Source

Technical

  • DocumentSub Division Plan.pdf · uploaded 10 Jan 2018Source
  • DocumentApproved Plan.PDF · uploaded 10 Jan 2018Source
  • DocumentBHIRANGI LANDMARK REVISED SANCTION.pdf · uploaded 29 Apr 2019Source

Technical (Architect)

  • DocumentForm 1 BLM Architect Certificate July 18.pdf · uploaded 16 Jul 2018Source

Technical (Engineer)

  • DocumentBLM ENGINEER CERTIFICATE JUNE 19.pdf · uploaded 3 Aug 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sangli Miraj Kupwad (M Corp.), Miraj taluka

Survey, CTS, gat or plot numbers

8357A

Boundaries

North
Public Road
South
Cs No 8358
East
CS No 8357B
West
Public Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Praveen Patil—
EngineerEr Pranav Kulkarni—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology