Skip to content

Shree Samarth Residency

Certificate Signed

Miraj, Maharashtra 416416 |Promoter: Shree Datta Pramotors & Builders

Residential / Group HousingRERAP53100023831
7 Jan 2020Registered with MahaRERA
30 Dec 2023Promised completion
1Building
23Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Office space23 units in all
Address
2272, 2272 Banugade Galli Miraj, BramhanpuriPIN 416416
Designated bank account
76
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2023

The latest completion date on record passed 2 years and 10 months ago.

Registered
7 Jan 2020
Promised
30 Dec 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P531000238317 Jan 202030 Dec 202330 Dec 2023Shree Datta Pramotors & BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shree Samarth Residency623

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 23 units booked (0%), as the promoter reported to MahaRERA

1BHK · 6 units2BHK · 11 unitsOffice space · 6 units
TypeCarpet areaUnitsBooked
1BHK32.1 sq m · 346 sq ft30
1BHK35.43 sq m · 381 sq ft30
2BHK36.3 sq m · 391 sq ft30
2BHK39.11 sq m · 421 sq ft40
2BHK44.92 sq m · 484 sq ft40
Office space32.1 sq m · 346 sq ft20
Office space35.43 sq m · 381 sq ft20
Office space36.3 sq m · 391 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN SHREE DATTA PROMO.pdf · uploaded 30 Dec 2019Source

Legal

  • Legal Title reportSEARCH REPORT.pdf · uploaded 16 Dec 2019Source
  • Declaration Form Bform b 1.pdf · uploaded 16 Dec 2019Source
  • Other – LegalFORMAT C REVISED.pdf · uploaded 14 Mar 2023Source

Migrated

  • 1 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 16 Dec 2019Source
  • 1 Details of encumbrancesencumbrance certificate.pdf · uploaded 16 Dec 2019Source
  • 1 Copy of Layout Approval (in case of layout)mojani nakasha.pdf · uploaded 16 Dec 2019Source
Show all 69 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentDWG 0.pdf · uploaded 16 Dec 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentBILDING PERMISSION.pdf · uploaded 16 Dec 2019Source
  • 1 Declaration in FORM Bform b 1.pdf · uploaded 16 Dec 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERIFICATE.pdf · uploaded 16 Dec 2019Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 16 Dec 2019Source
  • 2 Proforma of Allotment letterAGREEMENT OF SALES.pdf · uploaded 16 Dec 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE REVISED.pdf · uploaded 17 Dec 2019Source
  • 1 PAN CardPAN SHREE DATTA PROMO.pdf · uploaded 30 Dec 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 1 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate.pdf · uploaded 1 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2 a.pdf · uploaded 1 Apr 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)architect certificate.pdf · uploaded 1 Apr 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)c a certificate.pdf · uploaded 1 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)annual report statement 20-21.pdf · uploaded 1 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)annual report statement of accounts.pdf · uploaded 20 Feb 2023Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 31032020.pdf · uploaded 13 Mar 2023Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 31032021.pdf · uploaded 13 Mar 2023Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 31122021.pdf · uploaded 13 Mar 2023Source
  • 4 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 31032022.pdf · uploaded 13 Mar 2023Source
  • 5 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 30062022.pdf · uploaded 13 Mar 2023Source
  • 6 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD 30092022.pdf · uploaded 13 Mar 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentBUILDING DRAG REVISED 2_compressed.pdf · uploaded 14 Mar 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentBUILDING DRG 3.pdf · uploaded 14 Mar 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentConstruction permission PRWANA 2.pdf · uploaded 14 Mar 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentBANDHKAM PARVANA 3.pdf · uploaded 14 Mar 2023Source
  • 1 Declaration about Commencement Certificatedeclaration about commencement certificate.pdf · uploaded 14 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 1042020.pdf · uploaded 14 Mar 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 1042021.pdf · uploaded 14 Mar 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 1042022.pdf · uploaded 14 Mar 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE - 1072022.pdf · uploaded 14 Mar 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - 1102022.pdf · uploaded 14 Mar 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate 23012023.pdf · uploaded 14 Mar 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE 04042020-1.pdf · uploaded 14 Mar 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGIEERS CERTIFICATE - 04042022-3.pdf · uploaded 14 Mar 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE 04042021-2.pdf · uploaded 14 Mar 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE - 04072022-4.pdf · uploaded 14 Mar 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE 04072022-5.pdf · uploaded 14 Mar 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate.pdf · uploaded 14 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS CERTIFICATE FOR QUALITY ASSURANCE - 04042020.pdf · uploaded 14 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)ENGINEERS CERTIFICATE QUALITY ASSURANCE - 04042022.pdf · uploaded 14 Mar 2023Source
  • 7 Disclosure of sold/ booked inventorydisclosure of sold.pdf · uploaded 14 Mar 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE 31032020_compressed.pdf · uploaded 14 Mar 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE 31032021.pdf · uploaded 14 Mar 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE - 31032022.pdf · uploaded 14 Mar 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE - 30062022.pdf · uploaded 14 Mar 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE 30092022.pdf · uploaded 14 Mar 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)c a certificate.pdf · uploaded 14 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of intrest in other real estate organaisation - mahesh jamdar.pdf · uploaded 14 Mar 2023Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsdisclosure of intrest in other real estate organisation.pdf · uploaded 14 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 19-2020.pdf · uploaded 14 Mar 2023Source
  • 1 Other – LegalFORMAT C REVISED.pdf · uploaded 14 Mar 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentonkar dhulubulu letterhead FORM 4.pdf · uploaded 14 Mar 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)DEED OF DECLARATION_compressed (2).pdf · uploaded 14 Mar 2024Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion letter_1.pdf · uploaded 16 Mar 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)onkar dhulubulu letterhead FORM 4.pdf · uploaded 16 Mar 2024Source

Technical

  • Documentmojani nakasha.pdf · uploaded 16 Dec 2019Source
  • DocumentDWG 0.pdf · uploaded 16 Dec 2019Source
  • DocumentBUILDING DRAG REVISED 2_compressed.pdf · uploaded 14 Mar 2023Source
  • DocumentBUILDING DRG 3.pdf · uploaded 14 Mar 2023Source

Technical (Architect)

  • Documentarchitect certificate 23012023.pdf · uploaded 14 Mar 2023Source

Technical (Engineer)

  • Documentengineers certificate.pdf · uploaded 14 Mar 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

2272 at Miraj

Boundaries

North
2289 A 1 2289 B 2291 A 2
South
2275 B 2275 A 2273
East
Road And Cs No 2291 B 2291 A 2
West
2287

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmber M Shinde—
Chartered accountantHajare & Company—
Engineerrushikesh patil—
OtherPrakash Desai—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology