Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
PR1330002501414
Shiv-Kutir · Badlapur (M Cl), Thane · Koutilya Enterprises
Promised for 31 Dec 2029, extended to 30 Apr 2030, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2029 to 30 Apr 2030.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PR1330002501414
Is Shiv-Kutir delayed?
Its completion moved from 31 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PR1330002501414. The completion date moved from 31 Dec 2029 to 30 Apr 2030.
Who is the promoter?
MahaRERA records Koutilya Enterprises as the promoter of PR1330002501414.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PR1330002501414.
Answers are generated from the record.