Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered

PR1300002602368

Gajanan Pride · Sadarbazar, Satara · Gajanan Shinde Builders & Developers

Promised for 31 Dec 2031 and not extended so far.

5 years and 2 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate16 Oct 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1300002602368

Is Gajanan Pride delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2031, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1300002602368.

Who is the promoter?

MahaRERA records Gajanan Shinde Builders & Developers as the promoter of PR1300002602368.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1300002602368.

Answers are generated from the record.

Data through28 Oct 2026, 03:24SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology