RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
PR1180002501587
Paradigm Superstar · Bandra, Mumbai Suburban · Paradigm Framework LLP
Promised for 31 Mar 2029, extended to 31 Jul 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2029 to 31 Jul 2029.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PR1180002501587
Is Paradigm Superstar delayed?
Its completion moved from 31 Mar 2029 to 31 Jul 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PR1180002501587. The completion date moved from 31 Mar 2029 to 31 Jul 2029.
Who is the promoter?
MahaRERA records Paradigm Framework LLP as the promoter of PR1180002501587.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PR1180002501587.
Answers are generated from the record.
