RegisteredExtendedMahaRERA status: Certificate Signed

PR1180002500510

Garden Palacio · Ghatkopar, Mumbai Suburban · Maple Avenues LLP

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.

Documents 1

Registration certificate7 Aug 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1180002500510

Is Garden Palacio delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1180002500510. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Maple Avenues LLP as the promoter of PR1180002500510.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1180002500510.

Answers are generated from the record.

Data through23 Oct 2026, 02:22SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology