Vedah Phase 1 · Navsari, Amravati · Trendbuilt Lifespaces LLP
Promised for 31 Dec 2029, extended to 30 Apr 2030, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2029 to 30 Apr 2030.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PR1031012600010
Is Vedah Phase 1 delayed?
Its completion moved from 31 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PR1031012600010. The completion date moved from 31 Dec 2029 to 30 Apr 2030.
Who is the promoter?
MahaRERA records Trendbuilt Lifespaces LLP as the promoter of PR1031012600010.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PR1031012600010.